Canada makes scandium oxide, but still mines no rare earths.
The latest rare-earth mine total is zero. That does not mean Canada produces nothing. Scandium, indium and tellurium are already made, and 2026 brought real progress in processing, recycling and new critical-metal projects.
Updated 30 August 202626 minute readProject data cutoff 30 August 2026Price reference 28 August 2026
On this pageTakeaway
Canada's 2025 zero is a mining statistic, not a verdict on the whole materials sector. Quebec already recovers scandium from an existing industrial stream. Kingston recycles magnet material. Canadian refineries also make indium and tellurium, while Trail is an operating germanium and antimony site. The products, years and units differ, so they cannot be added into one national tonnage. 12025
The nearer rare-earth opportunity is processing. SRC began equipment testing in 2026 and targets commercial intake in the third quarter of 2027. Ucore produced customer samples, but remains a demonstration operation. No proposed conventional rare-earth mine was in financed construction by 30 August 2026. That is why the central 2030 case is zero to one mine beginning equipment testing, not a large Canadian mining boom. 211247
The country in four dates
The mine is late. The middle of the chain is moving.
Mine output, refinery output, recycling capacity and plant design are different measures. Every number below carries its year and production step. NdPr means neodymium and praseodymium reported together. Dy/Tb means dysprosium and terbium reported together. NdFeB means neodymium-iron-boron, the most common high-strength permanent magnet.
Reported 2025
Zero applies only to conventional rare-earth mines.
0 tonnescommercial primary rare-earth mine output in the USGS table1Scale: 0% of estimated 2025 world mine output.
40 tonnes · 3.6%indium refinery output and world share31
28 tonnes · 2.8%tellurium refinery output and world share33
Operatingscandium oxide route at Sorel-Tracy; current annual output not published20
What changed in 2026
Processors moved into equipment testing. New metal projects moved forward.
99.5% pureneodymium-praseodymium sample after more than 7,400 demonstration hours12
Early equipment testingSRC plant that turns partly processed minerals into metals21
Up to C$400 millionJuly framework for Trail expansion; definitive agreements still required24Scale: No total expansion cost or committed amount is disclosed, so a funded percentage cannot be calculated.
Construction startedRio Tinto gallium pilot designed for up to 4 tonnes a year23Scale: The four-tonne pilot is a different production step from the roughly 900-tonne world primary-output estimate, so no valid market share can be shown.
Likely in 2027
A processor may open. A new mine probably will not.
EarthRarest forecastSRC may take materialour forecast based on its third-quarter 2027 target; the plant is designed for 525 tonnes a year, not first-year output22Scale: The plant is designed for 525 tonnes a year, but no defensible first-year percentage exists until actual intake and output are reported.
EarthRarest forecast0 new minesour high-confidence forecast because none was in financed construction at the cut-off47
2030 view
One conventional mine at most begins equipment testing.
EarthRarest forecast0 to 1 mineour main forecast at year end47
Operating routeScandium oxide; 9 tonnes a year of expansion capacity would equal about 11% of estimated 2025 world primary output. Capacity is not output.
Ge
20 tonnes · 9.5%Primary output, 2022 benchmark
In
40 tonnes · 3.6%Refinery output, 2025
Te
28 tonnes · 2.8%Refinery output, 2025
Canada versus China
Four materials. Four like-for-like comparisons.
Each pair uses the same year and production step. Germanium is deliberately labelled as a 2022 benchmark.
About 5,200 tonnes a year of mixed rare-earth carbonate
Saleable mixed carbonate on an oxide-equivalent basis in the company study; the mine would also make a larger concentrate stream
Wicheeda is Canada's leading mine proposal. An early study estimates US$1.44 billion to build it. It still needs detailed engineering, permits, roads, power and construction finance. 45
Tardiff at Nechalacho
Vital Metals · Northwest Territories
Study only
Detailed study was targeted for 2026; no mine build had started by the data cut-off
56,000 tonnes a year of partly processed ore
Early plan for partly processed ore containing 26.4% rare-earth oxide
Tardiff is a new mine proposal, not a restart of the stopped North T pilot. Only an early study exists. Lenders still need a detailed cost study before they can consider financing construction. 6
Strange Lake
Torngat Metals · Quebec and Labrador
Waiting for money or permits
Assessment active August 2026
17,000 tonnes of ore a day
Mine, processing plant, road and coastal export route planned together
A long access road and new coastal route make infrastructure part of the project itself. C$165 million of announced loans supports preconstruction work, not a fully financed mine build. 78
Ashram
Mont Royal Resources · Nunavik, Quebec
Study only
A preliminary study is the next step
17,466 tonnes a year of mixed rare-earth carbonate, oxide equivalent
Company study, including 4,035 tonnes a year of neodymium-praseodymium
A 2026 company study estimates C$1.231 billion to build the mine, excluding the access road. It still needs a more detailed study, permits and finance, making production before 2030 unlikely. 9
SRC Rare Earth Processing Facility
Saskatchewan Research Council · Saskatoon, Saskatchewan
Testing output
Commercial intake targeted in the third quarter of 2027
525 tonnes a year of neodymium-praseodymium metal
Funded-upgrade design reported in August 2026; capacity is not 2027 output
SRC is Canada's processing plant closest to regular production. It plans to make neodymium-praseodymium metal and recover dysprosium and terbium. Buyer contracts cover most planned output, but the plant still has to prove that it can run steadily and supply paying customers. 1011
RapidSX demonstration plant
Ucore Rare Metals · Kingston, Ontario
Testing output
Verified August 2026
No annual output published
A high-purity sample proves the chemistry, not continuous production
The plant has proved that it can make a high-purity sample. It has not proved that a full-size factory can run continuously and deliver material accepted by paying customers. 1213
Material by material
What Canada can make now, what projects claim for 2030, and what China controls
Each card begins with the finding. The numbers and their limits sit underneath it.
Every bar runs from 0% to 100%. A solid bar is directly comparable. A shaded bar is an estimate or uses a different type of output. Where no reliable percentage exists, the card says so instead of drawing a false zero.
Canada nowIf projects openChina todayShaded: estimate or different output
Nd+Pr
Canada has a funded metal-line design, but no 2027 output total yet
NdPr: Neodymium and PraseodymiumElectric motors, wind turbines, robotics and defence magnets
Two different products: metal capacity and a mine study
NdNeodymiumPrPraseodymium
Canada nowNot enough data to calculate a share
If projects openCompany estimateAbout 3% to 5% of an older 2030 demand estimate if Ashram is built
China todayFour-material benchmark91% for Nd, Pr, Dy and Tb together (2024)
NowNo regular commercial total; SRC's funded upgrade is designed for 525 tonnes a year of neodymium-praseodymium metal
If projects openAshram study: 4,035 tonnes a year of neodymium-praseodymium content in mixed carbonate; not a production forecast
What it means: A processor can open before a Canadian mine, but designed capacity is not the amount it will make in 2027. 21, 22, 12, 9, 16, 18
The 525-tonne metal-line design and the 4,035-tonne mine study describe different products, so they are not added. The 3% to 5% comparison divides the Ashram study case by an older European Commission range for 2030 demand. It does not assume that the mine will be built. What these figures mean
SRC began equipment testing in 2026. Its funded upgrade is designed for 525 tonnes a year of neodymium-praseodymium metal. Ucore reports a 99.5%-pure sample from two raw-material sources. Ashram's early study estimates 4,035 tonnes a year of neodymium-praseodymium content inside mixed rare-earth carbonate. That is a project case, not operating output.
China figure: China refined 91% of neodymium, praseodymium, dysprosium and terbium together in 2024. This is not an individual-material share.
Dy+Tb
SRC now publishes a funded heavy-rare-earth design
Dy + Tb: Dysprosium and TerbiumMagnets that must keep working at high temperatures
DyDysprosiumTbTerbium
Canada nowNot enough data to calculate a share
If projects openNot enough data to calculate a share
China todayFour-material benchmark91% for Nd, Pr, Dy and Tb together (2024)
NowAmount not published
If projects open30 tonnes a year of dysprosium oxide
What it means: These are two different plant and product stages. Neither is current Canadian saleable output, and they must not be added. 21, 22, 9, 16
What these figures mean
SRC is testing equipment intended to recover dysprosium and terbium. It has not reported regular commercial sales. The funded upgrade is designed for 30 tonnes a year of dysprosium oxide and 15 tonnes a year of terbium oxide. Ashram's early study separately estimates about 100 tonnes a year combined inside mixed carbonate.
China figure: China refined 91% of neodymium, praseodymium, dysprosium and terbium together in 2024. This is not an individual-material share.
Sm+Gd
Government support, but no commercial samarium or gadolinium output
Sm + Gd: Samarium and GadoliniumSamarium-cobalt magnets, medical, optical and electronic uses
SmSamariumGdGadolinium
No published shareNo comparable percentage exists for current supply, planned supply or the China comparison at the same product stage.
NowAmount not published
If projects openAmount not published
What it means: Public money can help build the plant. It does not prove output or guarantee a selling price. 13, 17
What these figures mean
Ucore's Kingston work remains a test rather than commercial production. Ottawa conditionally offered up to C$36.3 million for a proposed samarium and gadolinium plant.
China figure: No like-for-like individual-material China share is published for this product stage.
Sc
Canada's funded expansion would lift scandium capacity to about 11% of today's world output
Sc: ScandiumLightweight aluminium alloys and solid-oxide fuel cells
Planned capacity compared with current world output
ScScandium
Canada nowNot enough data to calculate a share
If projects openPlanned capacityAbout 11% of current world output if the expansion runs at full capacity
China benchmarkReference benchmark66.7% in the 2016 to 2020 reference period
NowAmount not published
If projects openFunded design: 9 tonnes a year of scandium oxide; actual 2030 output is not published
What it means: Scandium is Canada's clearest operating rare-earth product, even though Canada has no commercial rare-earth mine. 20, 17, 19
The 11% comparison divides planned annual capacity of 9 tonnes by the USGS estimate of 80 tonnes of world scandium oxide output in 2025. Capacity is not production. What these figures mean
Rio Tinto already operates a scandium oxide plant at Sorel-Tracy in Quebec. A funded expansion is designed to lift annual capacity to 9 tonnes a year. Planned capacity is not the same as production or sales.
China figure: The European Commission estimated that China processed 66.7% of scandium in the 2016 to 2020 reference period.
China oxide price guide
Indicative domestic midpoints, 28 August 2026, per kilogram
LanthanumUS$0.72
CeriumUS$1.87
SamariumUS$2.17
YttriumUS$7.75
GadoliniumUS$25.62
NdPrUS$95.56
DysprosiumUS$191.78
TerbiumUS$889.95
Per kg of oxide. Purity, tax, delivery point, export licensing and contract terms can change a quote by multiples. These are not local sale-price forecasts. Source: SMM.
Strategic metals beyond rare earths
Canada's other strategic metals
These cards keep measured output, operating or recycling capacity and proposed projects separate. Capacity is not credited as output or market share. A data gap is not zero.
Sb
July 2026 capacity and plan context
Trail has antimony processing capacity, but no public tonnage.
This is not a Canadian mine-output figure. A conditional July 2026 framework could double Trail's existing antimony and germanium capacity, but gives neither tonnes nor a completion date and still requires definitive agreements and approvals.
Antimony: Flame retardants, lead-acid batteries, ammunition and infrared systems.
Existing capacity at TrailTonnes undisclosed
No reliable percentage is published for this country and production step.
Canada has no current bismuth figure in the USGS table.
NICO's company project case models 1,700 tonnes a year of bismuth for the first 14 years. The development-stage project gives no production start date, so this is neither current output nor operating capacity.
Bismuth: Medicines, lead-free solders, pigments and fusible alloys.
Not listed in the 2025 USGS tableNICO: 1,700 tonnes a year project case
No reliable percentage is published for this country and production step.
Canada recycles gallium, but no gallium-only output is published.
USGS does not list a Canadian primary low-purity figure for 2025. Peterborough's 25 to 35 tonnes a year of recycling and refining design capacity combines gallium and indium. Rio Tinto plans up to 4 tonnes a year of demonstration capacity for 2027; 40 tonnes a year is only a possible later commercial scale. A separate conditional July 2026 framework says Trail could add gallium capacity, without a tonnage or date.
Gallium: Power chips, radio-frequency chips, LEDs and high-efficiency solar cells.
No 2025 primary low-purity lineSecondary gallium-only output not published
No reliable percentage is published for this country and production step.
Canada's 20-tonne germanium figure is a 2022 benchmark.
The 9.5% share is not current output. Trail has existing germanium capacity, and the conditional July 2026 framework could double it, but gives no tonnage or completion date.
Germanium: Fibre optics, infrared optics, chips and specialist solar cells.
A deposit is only the first step. Statuses below describe operating capability at the data cut-off, not announced ambition.
01
No output
Mine
USGS estimated zero Canadian primary rare earth mine output in 2025. Wicheeda has a preliminary study, while Tardiff remains at scoping level. 146
02
Development
Concentrate
Several deposits have concentrate designs, but none supplies a sustained commercial Canadian stream. Old Nechalacho pilot material should not be mistaken for current production. 6
03
Start-up testing
Separation
SRC was conducting start-up tests on integrated solvent-extraction cells through 2026. Ucore was qualifying NdPr at demonstration scale in Kingston. 1012
04
Early output
Metals and alloys
SRC's funded upgrade is designed for 525 tonnes a year of neodymium-praseodymium metal, 30 tonnes of dysprosium oxide and 15 tonnes of terbium oxide. Five-year REalloys agreements cover most planned output. 11
05
Major gap
Permanent magnets
Canada has no established large commercial neodymium-iron-boron (NdFeB) magnet industry. China supplied almost 95% of sintered permanent magnets in 2024. 3
The numbers
The mine-output number in context
USGS 2025 estimates cover total rare earth oxide equivalent. The chart does not measure refining or magnet output.
Leading mine producers
World share and tonnes, 2025 estimate
China270,000 tonnes · 69.2% of world
United States51,000 tonnes · 13.1% of world
Australia29,000 tonnes · 7.4% of world
Myanmar22,000 tonnes · 5.6% of world
Canada0 tonnes · 0% of world
Every rail runs from 0% to 100% of world mine output. The label also gives tonnes. World total: about 390,000 tonnes in 2025; trade-derived estimates can be revised.
SRC remains the clearest test of Canada's processing-first thesis at an integrated facility. Its Saskatoon complex was built to move material through separation and into metal, with dedicated recovery for dysprosium or terbium alongside an NdPr stream. Integrated start-up testing of the full minerals-to-metals circuit continued through 2026. 10 REalloys signed five-year agreements covering the large majority of planned output. The funded upgrade is designed for 525 tonnes a year of neodymium-praseodymium metal, 30 tonnes of dysprosium oxide and 15 tonnes of terbium oxide. Those ratings are capacity, not a forecast of first-year output. The plant still has to prove steady production and customer acceptance. 11
Kingston provides a second route, with Ucore's commercial demonstration plant reporting more than 7,400 simulated-commercial operating hours by August 2026. It had produced 99.5% NdPr using raw material from Vietnamese ionic clay and North American bastnaesite, a useful stress test for a separation system that may have to accept changing sources. 12 Ottawa conditionally offered up to C$36.3 million for a proposed commercial Sm/Gd facility in Kingston. 13 Conditional support and sample tests remain several practical steps short of steady commercial output, with Ucore remaining in demonstration.
Stage labels hide just how sharply China's control changes along the rare earth chain. Natural Resources Canada put its share of mine production at 69% in 2024. Refining was far more concentrated, with China holding 90% of output. North America's 0.8% share at that stage makes separation Canada's first useful target rather than a side project. 2 The IEA places China's share of sintered permanent magnets at almost 95% for the same year. 3 A Canadian separation line can reduce one bottleneck without fixing the magnet layer. Finished oxides and metals will still need qualified allied customers, likely across the border or in Europe.
Imported raw material bridges the gap between an empty domestic mine column and a usable processing plant during this early phase. Sovereign branding becomes risky when it hides a vulnerable raw-material supply or imported specialist reagents. Even after both inputs are secured, final conversion may remain offshore. Canada should report origin and product form with every capacity claim. An origin-and-product-form label makes a 525-tonne-a-year metal plant more credible. A vague promise of thousands of tonnes from a mine still at an early study stage remains appropriately conditional.
Canada can become strategically useful before it becomes a large miner, provided the product passes customer tests and the raw-material route is disclosed.
What the numbers say
Wicheeda is Canada's clearest reserve-backed candidate, though final feasibility and permitting remain unfinished. The preliminary study carries initial capital around US$1.44 billion for the proposed operation. Planned dry concentrate output is 62,500 tonnes a year, making it more advanced than a project with only a resource estimate. 4 Ottawa offered up to C$1.88 million in 2026 for infrastructure studies rather than mine construction. One study covers a 60 km power connection from the existing grid. The road design is a separate 43 km assignment, a reminder that access is part of the mine plan. 5 Useful preparation does not yet amount to construction finance for the mine.
Tardiff in the Northwest Territories is larger on the resource page but one study stage earlier. Vital's 2025 scoping concept describes a starter operation producing 56,000 tonnes of concentrate a year. Initial capital was estimated at US$291 million, well below Wicheeda's study case but still untested by a preliminary study. 6 The earlier North T pilot stopped, and its processed stockpile does not make Tardiff an operating mine. Any table that carries the old producer label forward turns a discontinued trial into national output.
Strange Lake carries Canada's most visible infrastructure burden among the advanced northern proposals. The federal registry describes a mill designed to process 17,000 tonnes of ore each day. It would also need roughly 170 km of new road to the Labrador coast, making the transport corridor part of the project itself. 7 Torngat secured C$165 million across two loan facilities for preconstruction and infrastructure work. 8 Those facilities can fund serious preparation without amounting to a grant or full project finance. The impact statement and final build capital still separate the remote design from construction.
Ashram's June 2026 early economic study gives another strong case at 17,466 tonnes a year of rare-earth content in mixed carbonate, on an oxide-equivalent basis. NdPr accounts for about 4,035 tonnes of that annual product. The excluded infrastructure cost deserves equal attention. Initial capital is estimated at C$1.231 billion before the access road. 9 A long northern road is part of the mine cost, not an accessory added after the plant works. It also widens the assessment footprint for local or Indigenous communities.
Canada is putting more policy weight behind infrastructure and market-making rather than relying on exploration grants. Budget 2025 proposed a C$2 billion Critical Minerals Accelerator for strategic projects. The proposed five-year program starts in the 2026-27 fiscal year with loans or equity. Guarantees and purchase agreements remain available through separate instruments under the same proposal, a useful fit when lenders need confidence in both price and customer demand. 14 The harder public decision is which project receives enough support to reach a final build decision, since backing every study would scatter capital without creating supply.
Among the current candidates, Wicheeda has the most legible reserve and preliminary study route. Tardiff could offer a lower-capital starter concept if its preliminary study confirms the scoping work. Strange Lake carries a more integrated ambition with heavier infrastructure, while Ashram still needs to convert an early study into a tighter engineering case. Resource tonnes alone cannot rank projects at such different stages. Reserve quality and permitting set the order until committed finance turns a study into construction. A project only joins the race once construction actually begins.
Our most likely result by the end of 2030 is one Canadian mine beginning to test output, not four mines opening together. Processing plants should be further ahead. SRC could be operating its line, while Kingston plants test materials or handle recycling. Canadian raw material may enter that network late in the decade, but imported material is likely to remain important. Canada could still become a useful allied processing base even with mine output well below Australia or the United States.
A bear case remains plausible if rare earth prices weaken and northern capital costs rise. Canada would then finish the decade as a processing and project-development jurisdiction with no sustained primary mine. The optimistic case needs two mines financed and under construction early enough to begin trial production by 2030. Neither is that advanced today. Signed construction contracts and final approvals would change the picture. The final proof is steady output accepted by paying customers.
One mine in start-up testing by 2030 would validate the Canadian strategy. Four simultaneous starts would require a timetable the current files do not show.
EarthRarest forecast
Government help
How the government is helping projects get built in Canada
Loans, grants, guaranteed buyers and minimum prices can help a project get built. A promise counts only when the money or contract is committed.
Critical Minerals AcceleratorC$2 billionProposed loans and equity from 2026-27
Torngat preparation financeC$165 millionLoans, not full mine finance
Ucore conditional supportC$36.3 millionProposed Kingston Sm and Gd plant
Public national price floorNoneProject purchase agreements may still be negotiated
Measure
What it does
Who receives it
Will it move the project?
Critical Minerals Accelerator
Loans, equity, guarantees and purchase agreement toolsBudget 2025 proposed a five-year program beginning in 2026-27.
Strategic mines, infrastructure and processing projects selected by government.
A real financing tool, not an entitlementThe effect depends on which project receives enough support to reach construction. 14
Project preparation finance
C$165 million for Strange Lake preparationTwo facilities support preconstruction and infrastructure work.
Torngat's remote road and coastal route before full mine finance.
Road finance is part of mine financeThe loans advance engineering but do not fund the complete build. 8
Targeted technology support
Conditional grants and infrastructure studiesUcore has proposed Kingston support; Wicheeda received study funding for power and road work.
Customer testing and a road plan.
Useful before final build decision, insufficient after itSmall awards answer technical questions but cannot replace billion-dollar construction capital. 13, 5
Price and purchase agreement support
Available project by projectBudget tools allow purchase agreement or guarantees, but no public national NdPr, Dy or Tb floor is disclosed.
Only projects covered by a final contract.
No market-wide Canadian floorReaders should separate a policy power from a signed price-protection agreement. 14
EarthRarest forecast
What to watch through 2030
These are dated editorial predictions, not company guidance or investment advice. Each includes the evidence that would force a rethink.
By 31 December 2027
No Canadian mine produces meaningful output in 2027
No lead mine had reached a fully financed construction decision by August 2026. Wicheeda remained at the preliminary-study stage, while Tardiff had only completed scoping work. 46
ConfidenceHigh
What would change this view
Revise if Wicheeda, Tardiff or another Canadian asset reaches sustained commercial concentrate production before 2028.
During calendar 2027
Processing plants begin before mines
SRC targets commercial intake in the third quarter of 2027, while Ucore has already shown it can separate neodymium and praseodymium from more than one raw-material source in Kingston. Raw material from Canadian mines will not be ready on the same schedule. 2212
ConfidenceHigh
What would change this view
Revise if SRC commercial intake slips beyond the third quarter of 2027, products fail customer tests or a Canadian mine unexpectedly displaces imported raw material at scale.
At 31 December 2030
At most one mine begins testing production by 2030
Wicheeda has the most advanced case backed by a reported reserve. Tardiff is earlier. Strange Lake and Ashram have longer roads through infrastructure studies, permits and finance. The evidence supports one mine at most, not several projects opening together. 4679
ConfidenceMedium
What would change this view
Revise if one lead project reaches a fully financed final build decision by early 2028 with a credible shorter build, or if every leading project remains preconstruction at the end of 2030.
Method and evidence
What the numbers mean
Reserve and resource definitions
USGS reserves and NRCan's measured and indicated reserves/resources compilation are displayed separately. The broader NRCan total is not substituted for an economic reserve estimate. 12
Primary mining versus processing output
Zero mine output refers to commercial primary rare earth mining. Demonstration products, recycled oxide and processing of imported raw material are described at their actual stage rather than added to mine production.
Study cases and predictions
Early study and scoping outputs are company study cases rather than current production. The same rule applies to a preliminary study. EarthRarest forecasts carry an explicit condition that would change the view.
Nechalacho Scoping Study, Vital Metals, 28 July 2025. Tardiff starter concept, capital estimate and output design.
Strange Lake Rare Earth Mining Project registry, Impact Assessment Agency of Canada, Assessment commenced 8 November 2024, accessed 27 August 2026. Assessment status, mine plan and access-road scope.
Budget 2025, Chapter 1, Government of Canada, 4 November 2025. Canada Critical Minerals Accelerator design and funding.
SMM Rare Earth Oxides, assessed 28 August 2026. Domestic-China oxide midpoint indications used in the material price board.
International Energy Agency, Rare Earth Elements. China shares in 2024: 91% of combined Nd, Pr, Dy and Tb refining and 94% of sintered permanent magnets. These are group shares, not an individual share for each element.
SRC Rare Earth Processing Facility. Equipment-testing status and the schedule for substantial completion and operation in calendar 2027.
REalloys second-quarter 2026 results. Funded-upgrade design capacities of 525 tonnes a year of neodymium-praseodymium metal, 30 tonnes of dysprosium oxide and 15 tonnes of terbium oxide; commercial intake target in the third quarter of 2027.
Rio Tinto advances gallium pilot. Construction of a demonstration plant designed for up to four tonnes a year, with operation expected in 2027. A later 40-tonne commercial plant is only a possibility.
Canada announces Trail critical-minerals agreement. Framework for up to C$400 million that could double existing germanium and antimony capacity and add gallium; definitive agreements are still required.
Cyclic Materials opens Hub100. Operating Kingston recycling plant with capacity to process up to 100 tonnes a year of magnet feed into recycled mixed rare-earth oxide. Feed capacity is not oxide output.
USGS 2022 germanium country table. The latest complete country table estimates 20 tonnes of Canadian primary germanium in 2022. It is a dated benchmark, not current output.
Editorial artwork is illustrative and does not depict a named project site. Production and reserve figures are dated estimates. EarthRarest provides research and commentary, not personalised investment advice.
Continue when you’re ready
Bring us your questions.
Talk through the metals, the buying process, storage or resale with EarthRarest.