Editorial view of a Greenland rare earth mine beside an Arctic fjord with a concentrate ship offshore

Rare Earth Race · Country Briefing

Greenland has a licence, but no fully financed rare-earth mine.

Tanbreez has a legal route and proposed buyers. It still needs the money, construction and Arctic operating proof required for regular shipments.

Updated 30 August 202620 minute readProject data cutoff 27 August 2026Price reference 28 August 2026
On this pageTakeaway

Tanbreez would mine and concentrate rare earth ore in Greenland, then send the difficult chemical work abroad. Its first phase targets 15,000 tonnes a year of mixed concentrate, including heavy rare earth material intended for separation in the United States. The project has a 30-year licence, but no reported commercial output, declared mineral reserve or fully funded construction plan. The 1.5-million-tonne USGS figure is a national estimate; Tanbreez itself has not declared a mineral reserve. 2 5

The attraction is material diversity rather than a published annual total for any one oxide. Tanbreez has not disclosed reliable separated figures for neodymium, praseodymium, dysprosium or terbium. Proposed buyer contracts improve its route to market, while customer testing and US processing still have to work. 11 Greenland is unlikely to ship sustained commercial concentrate by the current 2029 target, and a domestic oxide or magnet plant is outside the 2030 base case. Kvanefjeld remains blocked after its mining application and licence renewal were rejected under the uranium rules. 17 18

The country in four dates

Geology is not the bottleneck. Execution is.

Reported output, current events, company targets and our forecasts are kept in separate boxes. NdPr means neodymium and praseodymium reported together. Dy/Tb means dysprosium and terbium reported together. NdFeB means neodymium-iron-boron, the most common high-strength permanent magnet.

Latest official position · 2025

A large reserve estimate, with no reported output.

  • No reported outputcommercial rare-earth mine output1
  • 1.5 million tonnesstock in the ground, under 2% of more than 75 million tonnes reported worldwide; not annual output1Scale: Under 2% of the more than 75 million tonnes reported worldwide. This is stock in the ground, not annual output.

What changed in 2026

Tanbreez gained routes to buyers, not full build finance.

  • US$30 millionacceleration programme8Scale: One quarter of the separate US$120 million export-credit indication. Neither figure is full project finance.
  • 15%share of Phase 1 planned concentrate in one proposed purchase route12
  • RejectedKvanefjeld licence renewal under current rules18

Next company target

Tanbreez aims for 2029, but the schedule is not funded.

  • Company targetthe third quarter of 2029Tanbreez company target5

2030 view

Greenland may export concentrate, not finished materials.

  • EarthRarest forecastLater than 2029our forecast for sustained commercial shipments5
  • EarthRarest forecastNo domestic oxide or magnet plantour main forecast5

Eight strategic metals

No national figure is reliable enough to compare

That does not mean the country has no projects. It means the public record does not support a like-for-like number for these eight metals.

See the check

Projects first

Tanbreez has a licence. Construction finance is still missing.

Tanbreez

Critical Metals Corp 92.5%; European Lithium 7.5% · Killavaat Alannguat, South Greenland

Study only

Technical report 13 April 2026

15,000 tonnes a year of concentrate

Latest Phase 1 design claim, not current production

A 30-year exploitation licence and community-benefit agreement are important assets. Greenland approved the transfer that took Critical Metals to 92.5% in April 2026. The current technical report still describes advanced exploration and resource delineation, with no mineral reserve or funded construction decision. 2 9 5 12

Tanbreez acceleration program

Critical Metals Corp · South Greenland

Study only

Announced 10 March 2026

First export targeted for the third quarter of 2029

Company target after first ore around late 2028 or early 2029

The US$30 million program advances field work and project definition. It does not cover the full cost of building the mine, formal approval to build or proof that all licence conditions are complete. 8

Ucore Louisiana purchase agreement

Ucore Rare Metals · Louisiana, United States

Testing output

Agreement 26 August 2025

Up to 10,000 tonnes a year of feed

Heavy rare earth concentrate contemplated for 10 years

Ucore provides a U.S. separation route backed by Department of Defense support. Its own move to steady output and testing of representative Tanbreez feed remain dependencies. 11

REalloys purchase agreement

REalloys and Critical Metals Corp · United States supply chain

Contract signed; first delivery pending

Signed 21 May 2026

15% of Phase 1

15-year term after first delivery; customer testing required

The contract is stronger than a memorandum of understanding, but the agreement can be cancelled if first delivery is not made within five years and the later-processing route must still make products accepted by customers. 12

Kvanefjeld / Kuannersuit

Energy Transition Minerals claimant · Near Narsaq, South Greenland

Stopped or blocked

Exploration renewal rejected 26 June 2026

No valid output case

The project has no legal construction or production path under current rules

The 2023 exploitation refusal, 2025 arbitration outcome and 2026 renewal rejection leave the uranium-bearing project legally stranded under current law. 17 18

Material by material

What Greenland supplies now, what could change by 2030, and China's share

Each card begins with the finding. The numbers and their limits sit underneath it.

Every bar runs from 0% to 100%. A solid bar is directly comparable. A shaded bar is an estimate or uses a different type of output. Where no reliable percentage exists, the card says so instead of drawing a false zero.

Greenland nowIf projects openChina todayShaded: estimate or different output
Mixed

The first product would leave Greenland unseparated

Mixed concentrateFeed for overseas separation plants

No published shareNo comparable percentage exists for current supply, planned supply or the China comparison at the same product stage.
NowNo commercial mine output reported at the cut-off
If projects openPhase 1 design: 15,000 tonnes a year of mixed concentrate; subject to finance and construction

What it means: A concentrate shipment would prove mining, not a Greenland oxide industry. 5, 8, 21

What these figures mean

Tanbreez is licensed but remains pre-construction, with no reported current mine output. Phase 1 targets 15,000 tonnes a year of concentrate and a company first-export target in 2029.

China figure: No like-for-like individual-material China share is published for this product stage.

Heavy

The strategic case is stronger than the tonnage label

Heavy rare earthsHeat-resistant magnets and specialist technologies

No published shareNo comparable percentage exists for current supply, planned supply or the China comparison at the same product stage.
NowNone reported
If projects openHeavy-rare earth content not published; up to 10,000 tonnes a year is the whole-concentrate amount contemplated for Ucore

What it means: Greenland's influence lies in feed diversity. It does not yet have commercial separated Dy or Tb. 11, 21

What these figures mean

Tanbreez material is intended for US separation, with up to 10,000 tonnes a year of contemplated feed. Qualification at Ucore and later downstream product output remain dependencies.

China figure: No like-for-like individual-material China share is published for this product stage.

Nd+Pr

Contained in the basket, not separately reported

NdPr: Neodymium and PraseodymiumHigh-volume permanent magnets

NdNeodymiumPrPraseodymium
Greenland nowNo reliable global percentage
If projects openNo reliable global percentage
China today91% for Nd, Pr, Dy and Tb together (2024)
NowAmount not published
If projects openAmount not published

What it means: A purchase agreement can help the project raise money, but it does not create a domestic separator. 12, 20

What these figures mean

The current Phase 1 disclosure does not provide a dependable annual separated-NdPr figure. A binding REalloys agreement covers 15% of Phase 1 production after qualification.

China figure: China refined 91% of neodymium, praseodymium, dysprosium and terbium together in 2024. This is not an individual-material share.

U + rare earth

The legal boundary matters

Uranium-bearing rare earth feedPotential mixed rare-earth and uranium recovery

No published shareNo comparable percentage exists for current supply, planned supply or the China comparison at the same product stage.
NowNone reported
If projects openAmount not published

What it means: Large resources can remain economically irrelevant when the permitted product route is blocked. 17, 18, 21

What these figures mean

Kvanefjeld has no valid construction route under current law after licence rejection and litigation. No output belongs in a forecast unless the legal position changes.

China figure: No like-for-like individual-material China share is published for this product stage.

China oxide price guide

Indicative domestic midpoints, 28 August 2026, per kilogram

LanthanumUS$0.72
CeriumUS$1.87
SamariumUS$2.17
YttriumUS$7.75
GadoliniumUS$25.62
NdPrUS$95.56
DysprosiumUS$191.78
TerbiumUS$889.95
Per kg of oxide. Purity, tax, delivery point, export licensing and contract terms can change a quote by multiples. These are not local sale-price forecasts. Source: SMM.

Strategic metals beyond rare earths

Greenland's other strategic metals

Each card states the type of output and year. The bars compare this country with the market leader at the same step whenever the data allows it. A data gap is not zero.

Compare all eight strategic metals

The conversion test

Where Greenland actually sits in the chain

A deposit is only the first step. Statuses below describe operating capability at the data cut-off, not announced ambition.

01
Licensed, pre-construction

Mine

Tanbreez has a 30-year exploitation licence, but the 2026 technical report still classifies it as advanced exploration and resource delineation. 2 5

02
Early-study design

Mineral concentrate

The preliminary design uses crushing and dry magnetic separation to make eudialyte and other mineral products. No commercial output has been reported. 7

03
Off-island dependency

Separation

Chemical processing is outside the scope of the Greenland study. Ucore and REalloys are proposed U.S. outlets that still require feed qualification and operating scale. 11 12

04
No domestic chain

Metals and alloys

No commercial Greenlandic oxide-to-metal or rare earth alloy plant was disclosed at the data cut-off.

05
No domestic chain

Permanent magnets

A Western purchase agreement is designed to connect Tanbreez to overseas magnet supply. It does not create a magnet industry with products that pass customer tests in Greenland. 12

The numbers

The mine-output number in context

USGS 2025 estimates cover total rare earth oxide equivalent. The chart does not measure refining or magnet output.

Leading mine producers

World share and tonnes, 2025 estimate
China 270,000 tonnes · 69.2% of world
United States 51,000 tonnes · 13.1% of world
Australia 29,000 tonnes · 7.4% of world
Myanmar 22,000 tonnes · 5.6% of world
Greenland Not reported
Every rail runs from 0% to 100% of world mine output. The label also gives tonnes. World total: about 390,000 tonnes in 2025; trade-derived estimates can be revised.

Greenland granted exploitation licence MIN 2020-54 over an 18-square-kilometre area in August 2020 for a 30-year term. The related impact benefit agreement sets annual targets for Greenlandic employment and local procurement. It also tracks education and training under the same local-benefit framework. Those decisions give Tanbreez a more serious legal and social base than an exploration prospect. 2 4

The licence does not authorize every activity, since the approved environmental documentation still requires detailed exploitation and closure plans. Construction and processes need separate approvals, as do vehicles and equipment. Critical Metals' annual filing also sets deadlines for plans and financial security, while exploitation must begin by the end of 2028. 3 6 Public material at this cut-off did not establish that every condition had been completed.

Critical Metals' April 2026 technical report is the strongest check on the phrase mine ready. It reports about 44.9 million tonnes across the Fjord and Hill zones, but it classifies Tanbreez as advanced exploration and resource delineation. The March 2025 economic assessment remains preliminary because it includes inferred material and declares no mineral reserve. 5 7

A US$30 million acceleration program approved by Critical Metals targets first ore around the turn of 2028-29, followed by concentrate exports in the third quarter of 2029. The Export-Import Bank's letter of interest covers up to US$120 million. Its proposed 15-year term does not turn the letter into committed debt or full project finance. 8 10 A credible schedule still needs finance and final approvals before construction can begin; production comes later.

The title is real. So are the uncompleted gates between a licensed deposit and a customer-invoiced shipment.

What the numbers say

The Tanbreez early study places crushing and dry magnetic separation at the Greenland site. Its design produces eudialyte and feldspar mineral products, with arfvedsonite recovered separately. Further mineral upgrading in the United States or Europe is explicitly outside the early study. 7 Limiting chemical processing at the Greenland site may simplify local waste handling, but it also sends processing risk and value abroad.

Eudialyte concentrate still has to be cracked, purified and separated into individual products such as neodymium, praseodymium, dysprosium and terbium oxides. Those oxides then need metal reduction, alloying and a magnet line whose products pass customer tests. A mine can ship on time while the strategic heavy rare earths remain trapped behind slow progress toward steady output at the later processing stage.

Ucore agreed to take up to 10,000 tonnes a year of heavy rare earth concentrate for its Louisiana facility. REalloys signed a binding purchase agreement in May 2026 covering 15% of Phase 1. The contract term begins with first delivery and runs for 15 years. Phase 1 is described at 15,000 tonnes of concentrate a year. Qualification is required, and a five-year cancellation deadline applies if first delivery does not occur. 11 12 Those conditions leave delivery risk open even though a buyer has signed.

The announced volumes should not be added because their scopes have changed or overlap. Earlier company material used a much larger tonnage for rare earth material, while Ucore described up to 10,000 tonnes of concentrate. REalloys now defines Phase 1 at 15,000 tonnes a year. EarthRarest uses the latest Phase 1 definition and keeps the other arrangements in their dated context.

Greenland's Mineral Resources Strategy 2025-2029 treats critical minerals as one route to economic diversification. It calls for closer EU cooperation and renewal of the United States minerals agreement. Geological mapping is another priority, with the Minerals Security Partnership Forum used to improve access to finance. 13 Partnership does not require Nuuk to approve every mineral deposit.

The EU and Greenland signed a raw materials memorandum in 2023. An EU factsheet says Greenland hosts 25 of the bloc's 34 critical raw materials. 14 15 American financing interest and purchase agreement pressure on Greenland have since grown. Multiple suitors let Greenland demand local jobs and public data before choosing an export route. Transparent revenue terms and infrastructure support can follow in the same negotiation.

Greenland's small population and lack of roads between settlements make each project a national economic decision. Dependence on fisheries raises the stakes further. An Arctic resource can be globally large while one missing road becomes a national budget problem. An ice-free fjord helps Tanbreez, but road and port works still need funding alongside the power supply. The benefit agreement turns those constraints into annual commitments that deserve public follow-up. 4

Greenlandic leaders have sought closer economic ties with both Europe and the United States while rejecting language that treats the territory as an asset to be acquired. The more accurate geopolitical story is competition to become Greenland's partner, under rules made in Nuuk. 16

Greenland's leverage comes from being able to choose between partners, and from being willing to leave some geology in the ground.

What the numbers say

Kvanefjeld, known locally as Kuannersuit, sat close to Narsaq and carried rare earths with uranium. Its proposed mine became central to Greenland's 2021 election as public concern focused on radioactive dust and tailings. Water risks became a separate fault line, while sheep farming and marine livelihoods also entered the debate around Narsaq. The uranium association defined the political choice rather than remaining a secondary by-product issue.

Greenland rejected the exploitation application on 1 June 2023 because it conflicted with the Uranium Act. After the refusal, the company sued in Greenland and pursued arbitration. The tribunal held in October 2025 that the claimed right to exploit could not be decided in that forum. Court proceedings continued, but litigation did not produce a licence. 17

The government's position hardened in June 2026 when Greenland rejected renewal of the exploration licence, finding that further exploration was unlikely to produce a deposit that could be exploited under the uranium law. 18 Kvanefjeld is therefore a legal and political case, not an advanced mine schedule.

No single developer can settle the wider lesson because Greenland wants mineral investment on terms that include credible waste controls and transparent local benefits. Respect for the island's power to say no remains part of what makes a project developable.

Government help

How the government is helping projects get built in Greenland

Loans, grants, guaranteed buyers and minimum prices can help a project get built. A promise counts only when the money or contract is committed.

Tanbreez licence30 yearsExploitation title, not final build decision
U.S. Export-Import Bank (EXIM) indicationUS$120 millionLetter of interest
Acceleration workUS$30 millionCompany field and engineering program
Binding purchase agreement15%REalloys share of Phase 1
MeasureWhat it doesWho receives itWill it move the project?
Exploitation licence and community-benefit agreementA legal right with community obligationsTanbreez holds a 30-year licence and an impact benefit agreement.The named Tanbreez project and local commitments.Necessary, not sufficientA licence still sits before full finance, construction and qualified product. 2, 4
US EXIM letter of interestIndicative export-credit supportUS$120 million is under consideration for Tanbreez.Mine development tied to an allied downstream route.Not committed construction financeDue diligence, final terms and the rest of the capital stack remain. 10
Long-term purchase agreementConditional future purchaseREalloys has a binding conditional agreement for 15% of Phase 1; Ucore contemplates a larger feed route.Qualified Tanbreez concentrate after first production.Better than a memorandum of understanding, still conditionalNo public floor price is disclosed, and outstanding conditions could still prevent first delivery. 12, 11
Mineral strategy and uranium lawProject selection through licensingGreenland seeks mining investment while the uranium-bearing Kvanefjeld route remains rejected.Projects compatible with current law and local consent.Policy favours some geology and blocks other geologyNational resource size cannot be read without the legal product boundary. 13, 17

EarthRarest forecast

What to watch through 2030

These are dated editorial predictions, not company guidance or investment advice. Each includes the evidence that would force a rethink.

By 30 September 2029

Tanbreez does not ship sustained commercial rare earth concentrate

The project remains pre-reserve and pre-construction, with detailed approvals, finance, Arctic infrastructure and testing by later processors ahead of the current third-quarter 2029 export target. 5 8

ConfidenceMedium
What would change this view

Revise if approved exploitation and closure plans, financial security, fully committed project finance, formal approval to build and an engineering and construction notice to proceed are all disclosed early enough to support trial production.

At 31 December 2030

Greenland still has no oxide or magnet factory.

Greenland has no commercial individual-oxide or sintered neodymium-iron-boron (NdFeB) plant. Tanbreez's onsite assessment ends at dry mineral concentration, and no financed Greenlandic separation or magnet project was disclosed. 7

ConfidenceHigh
What would change this view

Revise if a named Greenland site receives permits, binding finance and a construction contract for individual separation or customer-approved magnet production.

At 31 December 2030

Kvanefjeld still lacks a valid right to begin mine construction

Its exploitation application and exploration renewal were rejected, while arbitration did not establish a mining right under the current uranium framework. 17 18

ConfidenceHigh
What would change this view

Revise if the Uranium Act changes, a final court ruling overturns the refusal, or Greenland issues a new effective exploitation title and construction approvals.

Method and evidence

What the numbers mean

Resource, reserve and output
The 44.9-million-tonne Tanbreez figure is mineralized material across indicated and inferred classes. The 1.5-million-tonne USGS figure is a national rare-earth oxide reserve estimate. Neither is current output. 1 5
Licence stage
EarthRarest credits Tanbreez with its exploitation title and community-benefit agreement while separately tracking the exploitation plan, closure plan, activity approvals, security, finance and construction. 2 3
Company schedules
First ore, concentrate output and purchase agreement volumes are labelled as issuer targets or contract scopes. They are not included in present mine output.
Sources used for this briefing
  1. Mineral Commodity Summaries 2026: Rare Earths, U.S. Geological Survey, 6 February 2026, version 1.3 May 2026. Greenland production and reserve estimate.
  2. Tanbreez is granted an exploitation licence, Government of Greenland, Mineral Resources Authority, 13 August 2020. Licence area, term, community-benefit agreement and remaining plan requirements.
  3. Approved Environmental Impact Assessment: Tanbreez Mining Project, Government of Greenland and Tanbreez, 2014. Detailed exploitation, closure and activity approval requirements.
  4. Impact Benefit Agreement concerning the Killavaat Alannguat project, Government of Greenland, Kommune Kujalleq and Tanbreez, 8 September 2020. Local employment, procurement, training and annual monitoring.
  5. Amended and Restated Technical Report Summary on the Tanbreez Project, Critical Metals Corp, filed with the U.S. SEC, 13 April 2026. S-K 1300 resources, project classification and technical risks.
  6. Critical Metals Corp Annual Report on Form 20-F/A, Critical Metals Corp, filed with the U.S. SEC, 13 April 2026. Licence timetable, ownership chronology and risk disclosure.
  7. Tanbreez Greenland Rare Earths Project Preliminary Economic Assessment, Tanbreez and Agricola Mining Consultants, 31 March 2025. Preliminary resource and economics, no reserve, onsite dry concentration and excluded chemical processing.
  8. Critical Metals Corp accelerates the development of the Tanbreez project with an immediate US$30 million program, Critical Metals Corp, 10 March 2026. Program scope and company first-ore and export targets.
  9. Greenland government approves transfer of final 50.5% of Tanbreez, taking Critical Metals Corp to 92.5% ownership, Critical Metals Corp, 17 April 2026. Current Tanbreez ownership after Greenlandic approval.
  10. Critical Metals Corp secures US$120 million letter of interest from EXIM Bank for Tanbreez, Critical Metals Corp, 16 June 2025. Preliminary 15-year U.S. export-credit interest, not committed project finance.
  11. Critical Metals signs agreement to supply rare earth to US government-funded facility, Reuters, 26 August 2025. Ucore feed agreement, Louisiana separation route and U.S. support.
  12. REalloys signs definitive long-term rare earth Offtake Agreement with Critical Metals Corp for 15% of Tanbreez Phase 1 production, REalloys, 21 May 2026. Current Phase 1 scope, 15-year purchase agreement, qualification and cancellation deadline.
  13. Greenland Mineral Resources Strategy 2025-2029, Government of Greenland, 31 January 2025. Critical minerals, EU and U.S. cooperation, mapping and finance strategy.
  14. EU-Greenland memorandum on sustainable raw materials value chains, European Commission and Government of Greenland, 30 November 2023. Strategic partnership framework.
  15. The European Union and Greenland, European Commission, March 2024. Critical raw material presence, ice cover and economic context.
  16. Greenland wants more out of US defence agreement, minister says, Reuters, 15 May 2025. Greenlandic agency, economic diversification and EU-U.S. relations.
  17. After more than three years Naalakkersuisut wins in arbitration, Government of Greenland, 28 October 2025. Arbitration jurisdiction outcome and continuing court context.
  18. Greenland rejects Energy Transition Minerals' request for licence renewal, Reuters, republished by Kitco, 26 June 2026. Latest exploration renewal rejection under the uranium-law framework.
  19. SMM Rare Earth Oxides, assessed 28 August 2026. Domestic-China oxide midpoint indications used in the material price board.
  20. International Energy Agency, Rare Earth Elements. China shares in 2024: 91% of combined Nd, Pr, Dy and Tb refining and 94% of sintered permanent magnets. These are group shares, not an individual share for each element.
  21. European Commission, Study on the Critical Raw Materials for the EU 2023. Processing-share estimates use the 2016 to 2020 reference period and are labelled as reference values, not current 2026 shares.
Editorial artwork is illustrative and does not depict a named project site. Production and reserve figures are dated estimates. EarthRarest provides research and commentary, not personalised investment advice.

Continue when you’re ready

Bring us your questions.

Talk through the metals, the buying process, storage or resale with EarthRarest.

Speak with us How buying works

EarthRarest rare earth intelligence

Rare Earth Mining Race

Follow the mines, separation plants and magnet projects shaping supply through 2030.

Explore the rare earth mining race