Research database
Rare earth projects tracker
Compare 103 project, facility and operating-chain records across 20 country briefings. Each row preserves its reported status, product basis, conditions and source links.
Compiled: 19 October 2026 · Original reporting cutoffs: 2026-08-27/2026-08-30
This is a dated consolidation, not a fresh October status check. “Producing now” and similar status labels describe the original briefing's cutoff. Check the linked source and newer company disclosures before relying on a project milestone.
Read the product before comparing the amount
A tonne of ore, mixed carbonate, contained rare-earth oxide, separated oxide, metal or magnet describes a different stage. Planned capacity is not actual output. Linked mines and processing plants may use the same material, so adding their figures would double-count supply. This tracker deliberately publishes no total capacity.
Operators and locations retain the source's wording. Australia's source table supplies locations without a separate operator field. First-production dates appear only when present in the original row; conditions and dates remain attached to the claim. The tracker is not a complete list of every project worldwide.
Download tracker CSV · Download tracker JSON with methodology
Project and facility records
103 records
No projects match these filters.
| Project, operator or location | Reported status | Product and amount, original basis | Conditions and dependencies | Cutoff and sources |
|---|---|---|---|---|
| Longonjo Stage 1 Pensana 84%; Angola's sovereign wealth fund (FSDEA) 10%; other investors 6% · Near Longonjo, Huambo Province Angola briefing | Under construction 22% complete as of 8 June 2026 | 20,000 tonnes a year of mixed rare-earth carbonate Stage 1 product mass, not contained rare-earth oxide | Earthworks and site facilities were real, while the US$150 million balance had not been received by the cut-off. That delay put the 2027 trial production target under pressure. | Cutoff: 2026-08-27Sources and original notes
|
| Longonjo heavy rare earth circuit Pensana · Longonjo processing plant Angola briefing | Study only Target disclosed 8 June 2026 | >122 tonnes a year of Dy/Tb Optimization target; not current designed output | The ore contains strategic heavy rare earths, but the higher-recovery circuit still needs engineering and commercial proof. Do not convert its target into operating supply. | Cutoff: 2026-08-27Sources and original notes
|
| Longonjo Stage 2 Pensana · Huambo Province Angola briefing | Study only Year-four target restated June 2026 | 40,000 tonnes a year of mixed rare-earth carbonate Expanded product-mass target | Stage 2 doubles the first train's headline output. It depends on Stage 1 reaching steady output, fresh capital and buyers, leaving the 2029 timing outside the most likely forecast. | Cutoff: 2026-08-27Sources and original notes
|
| Lobito Atlantic Railway Lobito Atlantic Railway concession; U.S. International Development Finance Corporation (DFC) lender · Lobito to Angola's eastern border Angola briefing | Under construction US$553 million loan signed 17 December 2025 | 1,300 km corridor Transport capacity, not rare earth output | The corridor gives Longonjo an export route and Western policy relevance. Mine-specific loading, tariffs and service reliability still need contracts. | Cutoff: 2026-08-27Sources and original notes
|
| Toyota Tsusho and TREI route Toyota Tsusho; Toyotsu Rare Earths India · India later-processing route Angola briefing | Study only Restated 8 June 2026 | Up to 20,000 tonnes a year of mixed rare-earth carbonate Five-year contemplated intake | The route could absorb Stage 1 output through an established Japanese-linked processor. Pricing and binding minimum volumes were not final in the cited update. | Cutoff: 2026-08-27Sources and original notes
|
| ReElement and VAC/eVAC route ReElement Technologies and VAC/eVAC · Indiana and South Carolina, United States Angola briefing | Study only Restated 8 June 2026 | No binding volume disclosed Proposed U.S. separation-to-magnet branch | The agreements make the U.S. strategy visible, but a memorandum-of-understanding diagram is not a shipment. Qualification and finance conditions need to close before it becomes a chain that lenders can finance. | Cutoff: 2026-08-27Sources and original notes
|
| Mt Weld and Kalgoorlie Western Australia Australia briefing | Producing now | Mined in Australia: 29,000 tonnes in 2025 Lynas products later made in Malaysia: 13,089 tonnes in the 2026 financial year | Earliest supply: Now Large-scale operating chain Kalgoorlie makes mixed carbonate. Lynas's reported oxides ready to sell are separated and finished in Malaysia. Source | Cutoff: 2026-08-28Sources and original notes
|
| Balranald New South Wales Australia briefing | Producing now | Actual 2026 output not yet published Earlier full-rate estimate: about 4,000 tonnes a year of concentrate; not finished rare-earth chemicals | Earliest supply: Mining began January 2026 Rare-earth raw material follows the refinery schedule Monazite-rich mineral sands are intended for Eneabba. Current project , estimate | Cutoff: 2026-08-28Sources and original notes
|
| Eneabba refinery Western Australia Australia briefing | Under construction | Full-rate project case: 15,100 tonnes a year Includes 3,300 tonnes of neodymium-praseodymium. The 23,000-tonne maximum needs enough suitable raw material; neither figure is 2027 output | Earliest supply: Testing in 2027 First contracted deliveries in 2028 Turns stockpile and mined raw material into oxides in Australia. It is a processor, not extra mine supply. Case , schedule | Cutoff: 2026-08-28Sources and original notes
|
| Nolans Northern Territory Australia briefing | Funded; mobilisation under way | 4,440 tonnes of neodymium-praseodymium chemicals Full design output, plus about 570 tonnes of combined middle and heavy rare-earth products in the economics case | Earliest supply: Major construction targeted from September 2026 Mid-2029 first-product target Mine, chemical treatment and oxide separation are planned on one Australian site. Decision , output | Cutoff: 2026-08-28Sources and original notes
|
| Browns Range Western Australia Australia briefing | Waiting for money or permits | 17,500 tonnes of partly processed ore Study estimate containing about 4,350 tonnes of rare-earth material, rich in dysprosium and terbium | Earliest supply: Late 2028 or early 2029 target Conditional on a build decision and finance Planned raw material for Eneabba. Important for material mix, not just tonnes. Study , schedule | Cutoff: 2026-08-28Sources and original notes
|
| Yangibana Western Australia Australia briefing | Waiting for money or permits | 31,570 tonnes of partly processed ore Study estimate containing 8,524 tonnes of rare-earth material and 3,090 tonnes of neodymium and praseodymium | Earliest supply: About two years after engineering and construction award Decision and finance still required Large study figure, but excluded from the central 2030 case until a build is funded. Source | Cutoff: 2026-08-28Sources and original notes
|
| Dubbo New South Wales Australia briefing | Waiting for money or permits | 1,242 tonnes of individual rare-earth chemicals Earlier study case. The current product route is being reviewed | Earliest supply: No dependable date Design may change Could make mixed or separated products. Earlier case , review | Cutoff: 2026-08-28Sources and original notes
|
| Donald Victoria Australia briefing | Waiting for money or permits | 8,500 to 9,500 tonnes of partly processed ore Current company production target | Earliest supply: 2028 company target Conditional on a final build decision and debt finance Concentrate is intended for separation in Utah, United States. Source | Cutoff: 2026-08-28Sources and original notes
|
| Goschen Victoria Australia briefing | Waiting for money or permits | 8,320 tonnes of partly processed ore Agreement average containing about 4,900 tonnes of rare-earth material | Earliest supply: No dependable date Environmental approval is in place; a final build decision and finance remain conditions Intended raw material for Eneabba. Do not add its contained tonnes to Eneabba output. Source | Cutoff: 2026-08-28Sources and original notes
|
| Pela Ema Serra Verde; USA Rare Earth acquisition pending at the data cut-off · Goias Brazil briefing | Producing now Since January 2024 | More than 5,000 tonnes a year of mixed rare-earth carbonate Original full-output plan; 6,400-tonne-a-year target by the end of 2027 | Brazil's only commercial rare earth mine is the reference case. The expansion, change of ownership and long-term US purchase agreement remained forward-looking on 27 August 2026. | Cutoff: 2026-08-27Sources and original notes
|
| Carina Aclara Resources · Goias Brazil briefing | Waiting for money or permits Feasibility study filed in April 2026 | 4,378 tonnes a year of mixed rare-earth carbonate Company feasibility case | A pilot plant and filed study reduce technical uncertainty, but environmental approval, finance and construction still gate the 2028 target. | Cutoff: 2026-08-27Sources and original notes
|
| Caldeira Meteoric Resources · Minas Gerais Brazil briefing | Study only Preliminary study August 2025; POSCO pact July 2026 | 13,584 tonnes a year of mixed rare-earth carbonate Preliminary-study production case | The largest near-term proposal has a serious strategic partner but no final investment decision. Its company schedule should be read as conditional. | Cutoff: 2026-08-27Sources and original notes
|
| Colossus Viridis Mining and Minerals · Minas Gerais Brazil briefing | Testing output Preliminary study July 2025; demo active in 2026 | About 9,500 tonnes a year of mixed rare-earth carbonate Preliminary-study concept | The demonstration centre can produce customer samples. It does not prove that a full-scale mine will meet the company's end-of-2028 schedule. | Cutoff: 2026-08-27Sources and original notes
|
| Monte Alto Brazilian Rare Earths · Bahia Brazil briefing | Study only Trial licence June 2026 | Annual trial cap: 2,000 tonnes Sampling allowance, not commercial output | High-grade results justify more work. A trial mining limit and drilling programme are not a reserve, financed plant or production forecast. | Cutoff: 2026-08-27Sources and original notes
|
| MagBras Brazilian research and industrial consortium · Minas Gerais Brazil briefing | Evidence limited Government visit May 2026 | No commercial tonnes disclosed Magnet development and recycling work | MagBras can preserve process knowledge and train a workforce. It is not evidence of a scaled domestic sintered magnet industry. | Cutoff: 2026-08-27Sources and original notes
|
| Wicheeda Defense Metals · British Columbia Canada briefing | Study only Feasibility and infrastructure work under way | About 5,200 tonnes a year of mixed rare-earth carbonate Saleable mixed carbonate on an oxide-equivalent basis in the company study; the mine would also make a larger concentrate stream | Wicheeda is Canada's leading mine proposal. An early study estimates US$1.44 billion to build it. It still needs detailed engineering, permits, roads, power and construction finance. | Cutoff: 2026-08-30Sources and original notes
|
| Tardiff at Nechalacho Vital Metals · Northwest Territories Canada briefing | Study only Detailed study was targeted for 2026; no mine build had started by the data cut-off | 56,000 tonnes a year of partly processed ore Early plan for partly processed ore containing 26.4% rare-earth oxide | Tardiff is a new mine proposal, not a restart of the stopped North T pilot. Only an early study exists. Lenders still need a detailed cost study before they can consider financing construction. | Cutoff: 2026-08-30Sources and original notes
|
| Strange Lake Torngat Metals · Quebec and Labrador Canada briefing | Waiting for money or permits Assessment active August 2026 | 17,000 tonnes of ore a day Mine, processing plant, road and coastal export route planned together | A long access road and new coastal route make infrastructure part of the project itself. C$165 million of announced loans supports preconstruction work, not a fully financed mine build. | Cutoff: 2026-08-30Sources and original notes
|
| Ashram Mont Royal Resources · Nunavik, Quebec Canada briefing | Study only A preliminary study is the next step | 17,466 tonnes a year of mixed rare-earth carbonate, oxide equivalent Company study, including 4,035 tonnes a year of neodymium-praseodymium | A 2026 company study estimates C$1.231 billion to build the mine, excluding the access road. It still needs a more detailed study, permits and finance, making production before 2030 unlikely. | Cutoff: 2026-08-30Sources and original notes
|
| SRC Rare Earth Processing Facility Saskatchewan Research Council · Saskatoon, Saskatchewan Canada briefing | Testing output Commercial intake targeted in the third quarter of 2027 | 525 tonnes a year of neodymium-praseodymium metal Funded-upgrade design reported in August 2026; capacity is not 2027 output | SRC is Canada's processing plant closest to regular production. It plans to make neodymium-praseodymium metal and recover dysprosium and terbium. Buyer contracts cover most planned output, but the plant still has to prove that it can run steadily and supply paying customers. | Cutoff: 2026-08-30Sources and original notes
|
| RapidSX demonstration plant Ucore Rare Metals · Kingston, Ontario Canada briefing | Testing output Verified August 2026 | No annual output published A high-purity sample proves the chemistry, not continuous production | The plant has proved that it can make a high-purity sample. It has not proved that a full-size factory can run continuously and deliver material accepted by paying customers. | Cutoff: 2026-08-30Sources and original notes
|
| Bayan Obo integrated system China Northern Rare Earth and Baotou Steel group companies · Baotou, Inner Mongolia China briefing | Producing now Status filed 18 April 2026 | Mine feed and separated oxides The anchor of China's northern light-rare-earth cluster | The group reported record operating volumes for 2025 but withheld the detailed published product breakdown under secrecy provisions. That makes the asset strategically central and unusually difficult to model from public data. | Cutoff: 2026-08-27Sources and original notes
|
| Northern Rare Earth green smelting upgrade China Northern Rare Earth · Baotou, Inner Mongolia China briefing | Operating; expansion building Status filed 18 April 2026 | Cleaner separation and refining Phase two remained under construction | The approved investment ceiling is RMB 7.799 billion. This is an expansion at an operating site inside an operating cluster, so it carries less integration risk than a remote new refinery built from scratch. | Cutoff: 2026-08-27Sources and original notes
|
| JL MAG operating magnet base JL MAG Rare-Earth · Jiangxi and Baotou operations China briefing | Producing now Status filed 1 April 2026 | High-performance neodymium-iron-boron (NdFeB) magnets Serving vehicles and industrial motors, including wind systems | Designed annual capacity stood at 40,000 tonnes at the end of 2025. Utilization exceeded 90 percent, which separates this operation from the many announced lines elsewhere that have not yet won customer approval. | Cutoff: 2026-08-27Sources and original notes
|
| JL MAG Baotou Phase III JL MAG Rare-Earth · Baotou, Inner Mongolia China briefing | Under construction Status filed 1 April 2026 | Additional sintered NdFeB capacity Built beside a mature materials cluster | The phase adds 20,000 tonnes of annual high-performance magnet capacity. Management targets total designed capacity of 60,000 tonnes by the end of 2027. | Cutoff: 2026-08-27Sources and original notes
|
| Ganzhou metal and alloy relocation China Rare Earth Group subsidiary · Ganzhou, Jiangxi China briefing | Study only Approval published 7 May 2025 | Rare earth metals and alloys A processing project, not a new mine | The approved project is designed for 8,000 tonnes of rare earth metals and alloys a year. Its value lies between oxide separation and magnets, the part of the chain many rival countries still send abroad. | Cutoff: 2026-08-27Sources and original notes
|
| Daping heavy rare earth prospect China Rare Earth Group · Lanshan County, Hunan China briefing | Study only Proposed transfer published 17 October 2025 | Heavy rare earth exploration No commercial production declared | Hunan proposed transferring the exploration right to China Rare Earth Group. The project may improve domestic heavy-feed options, but an exploration title should not be counted as mine supply. | Cutoff: 2026-08-27Sources and original notes
|
| Tanbreez Critical Metals Corp 92.5%; European Lithium 7.5% · Killavaat Alannguat, South Greenland Greenland briefing | Study only Technical report 13 April 2026 | 15,000 tonnes a year of concentrate Latest Phase 1 design claim, not current production | A 30-year exploitation licence and community-benefit agreement are important assets. Greenland approved the transfer that took Critical Metals to 92.5% in April 2026. The current technical report still describes advanced exploration and resource delineation, with no mineral reserve or funded construction decision. | Cutoff: 2026-08-27Sources and original notes
|
| Tanbreez acceleration program Critical Metals Corp · South Greenland Greenland briefing | Study only Announced 10 March 2026 | First export targeted for the third quarter of 2029 Company target after first ore around late 2028 or early 2029 | The US$30 million program advances field work and project definition. It does not cover the full cost of building the mine, formal approval to build or proof that all licence conditions are complete. | Cutoff: 2026-08-27Sources and original notes
|
| Ucore Louisiana purchase agreement Ucore Rare Metals · Louisiana, United States Greenland briefing | Testing output Agreement 26 August 2025 | Up to 10,000 tonnes a year of feed Heavy rare earth concentrate contemplated for 10 years | Ucore provides a U.S. separation route backed by Department of Defense support. Its own move to steady output and testing of representative Tanbreez feed remain dependencies. | Cutoff: 2026-08-27Sources and original notes
|
| REalloys purchase agreement REalloys and Critical Metals Corp · United States supply chain Greenland briefing | Contract signed; first delivery pending Signed 21 May 2026 | 15% of Phase 1 15-year term after first delivery; customer testing required | The contract is stronger than a memorandum of understanding, but the agreement can be cancelled if first delivery is not made within five years and the later-processing route must still make products accepted by customers. | Cutoff: 2026-08-27Sources and original notes
|
| Kvanefjeld / Kuannersuit Energy Transition Minerals claimant · Near Narsaq, South Greenland Greenland briefing | Stopped or blocked Exploration renewal rejected 26 June 2026 | No valid output case The project has no legal construction or production path under current rules | The 2023 exploitation refusal, 2025 arbitration outcome and 2026 renewal rejection leave the uranium-bearing project legally stranded under current law. | Cutoff: 2026-08-27Sources and original notes
|
| OSCOM mineral-sands complex IREL (India) Ltd · Chatrapur, Odisha India briefing | Producing now Verified August 2026 | 7.5 million tonnes of sand a year Mineral-sands throughput, not rare earth output | OSCOM supplies the state chain and hosts rare earth extraction, but its large mining figure covers the full sand stream. National 2025 mine output was only 2,900 tonnes of rare-earth oxide equivalent on the comparable USGS basis. | Cutoff: 2026-08-27Sources and original notes
|
| Rare Earth Extraction Plant IREL (India) Ltd · Odisha India briefing | Producing now Current chain verified August 2026 | Mixed rare earth chloride Intermediate product made from recovered monazite | The plant cracks monazite and moves India beyond mineral concentrate. Feed remains limited by coastal mine access, with government reporting actual monazite production around 4,000 tonnes a year. | Cutoff: 2026-08-27Sources and original notes
|
| Rare Earths Division, Aluva IREL (India) Ltd · Kerala India briefing | Producing now Product slate verified August 2026 | >99% separated oxides Mainly light rare earths; the basis of the stated 4,000-tonne figure is unclear | Aluva proves that India can make individual high-purity oxides. The public statement does not say which period or product its capacity figure covers, so no annual saleable output can be calculated. | Cutoff: 2026-08-27Sources and original notes
|
| Sintered rare-earth permanent magnet manufacturing scheme Ministry of Heavy Industries and selected firms · Sites pending beneficiary selection India briefing | Study only 20 bids reported 13 August 2026 | NdFeB magnet target: 6,000 tonnes a year Policy ceiling, not installed capacity | The program is meant to convert oxide into metal, then metal into alloy and finished magnets. Strong bidder interest still leaves beneficiary awards and construction ahead. Lengthy customer testing follows. | Cutoff: 2026-08-27Sources and original notes
|
| Puri and Brahmagiri mineral-sands expansion IREL joint ventures · Odisha India briefing | Study only Portfolio status August 2026 | No rare-earth oxide figure disclosed Feed expansion projects without a public schedule | Puri is listed under implementation, while Brahmagiri still needs statutory mining-lease clearances. Their contribution should remain unmodelled until IREL publishes product basis and timing. | Cutoff: 2026-08-27Sources and original notes
|
| Nawatola-Laband rare earth block Hindustan Zinc Exploration Services · Uttar Pradesh India briefing | Study only Surface work began in the final quarter of the 2026 financial year | No reserve or mine plan Composite licence pathway, not production | This is the clearest private hard-rock exploration milestone. It has no reported reserve or processing tests yet, so even a mine-development timetable would be premature. | Cutoff: 2026-08-27Sources and original notes
|
| Caremag Carester with Japan's state minerals agency and Iwatani support · Lacq, France Japan briefing | Under construction Japan-France roadmap reaffirmed 1 April 2026 | About 20% of Japan's future Dy/Tb demand Japan's industry ministry expectation under long-term supply, not current output | Japanese and French public backing targets recycled magnets and primary feed. Trial production and heavy-oxide output ready to sell remain the commercial tests. | Cutoff: 2026-08-27Sources and original notes
|
| Minamitorishima rare-earth mud Japan's marine science agency and the national ocean programme · Japan's exclusive economic zone, western Pacific Japan briefing | Testing output Results published 24 July 2026 | About 50 tonnes of mud recovered Three-day test material, not rare-earth oxide product | Continuous lifting from a 5,569-metre pipe depth is a genuine engineering milestone. A longer 2027 test and March 2028 economic assessment stand between this result and any industrial decision. | Cutoff: 2026-08-27Sources and original notes
|
| Mandena and Port Ehoala QIT Madagascar Minerals · Fort Dauphin, Anosy Madagascar briefing | Producing now Verified August 2026 | 2,700 tonnes of national rare-earth mine output USGS 2025 country estimate, not QMM reported output | Rio Tinto's QIT Madagascar Minerals (QMM) operation is the established monazite route, but the exact 2025 company contribution is not separately reported in the USGS table. Current product leaves through Port Ehoala before individual oxide separation. | Cutoff: 2026-08-27Sources and original notes
|
| Ampasindava Harena Resources · Ampasindava Peninsula Madagascar briefing | Study only Mining terms signed 11 August 2026 | About 4,000 tonnes a year of total rare-earth oxide Preliminary study forecast, including about 1,700 tonnes a year of combined NdPr, Dy and Tb | A completed preliminary study and U.S. International Development Finance Corporation (DFC) development grant move Ampasindava beyond a resource story. Environmental approval, full construction finance and formal approval to build remain requirements before the mid-2028 company target. | Cutoff: 2026-08-27Sources and original notes
|
| Vara Mada Energy Fuels · Atsimo-Andrefana Madagascar briefing | Waiting for money or permits Verified June quarter 2026 | Monazite from 2029 target Company schedule; intended for White Mesa in Utah | The suspension is lifted, but monazite is not yet included in the exploitation permit. Fiscal terms, full construction finance and formal approval to build also remain outstanding, so the early-2029 delivery case is still conditional. | Cutoff: 2026-08-27Sources and original notes
|
| Kenering non-radioactive rare earths mine Perak state and private operating structure · Hulu Perak Malaysia briefing | Producing now Operating since September 2022; regulator status March 2026 | 5,139 tonnes of rare-earth carbonate Gross cumulative carbonate through August 2023 | Kenering remains Malaysia's only fully approved operating rare earth mine. The reported carbonate mass needs assay before it can be compared with USGS contained-rare-earth oxide output. | Cutoff: 2026-08-27Sources and original notes
|
| Lynas Malaysia Lynas Rare Earths · Gebeng, Pahang Malaysia briefing | Producing now Ten-year licence effective 3 March 2026 | 13,089 tonnes of rare-earth oxide 2026 financial-year company-wide ready-for-sale total; separation in Malaysia | The facility is an operating ex-China separator with Dy and Tb capability. Its feed is predominantly Australian, so the production line belongs beside Malaysian processing rather than local mining. | Cutoff: 2026-08-27Sources and original notes
|
| Lynas heavy rare earth expansion Lynas Rare Earths · Gebeng, Pahang Malaysia briefing | Study only Announced October 2025; pending approvals as of August 2026 | Feed capacity: up to 5,000 tonnes a year Heavy-feed capacity, not finished oxide tonnes | A$180 million of proposed investment would widen the product slate. Construction timing still depended on regulatory approval and a purchase agreement. | Cutoff: 2026-08-27Sources and original notes
|
| JS Link Kuantan magnet factory JS Link with Lynas partnership · Kuantan, Pahang Malaysia briefing | Funded, work not started Partnership announced 6 July 2026 | 3,000 tonnes a year of neodymium-iron-boron (NdFeB) magnets Planned design, no commercial output yet | The supply agreement and Lynas investment make this more concrete than a loose memorandum of understanding. Site construction and shipments accepted by customers remained ahead. | Cutoff: 2026-08-27Sources and original notes
|
| Carester-Malaco Perak project Carester and Malaco Mining Group · Perak Malaysia briefing | Waiting for money or permits Joint venture detailed 6 July 2026 | About 13,000 tonnes a year Proposed separation capacity; product basis not fully disclosed | The partners were still seeking mining permission and gave no cost or schedule. Technology transfer may matter later, but no tonnes belong in a most likely supply forecast yet. | Cutoff: 2026-08-27Sources and original notes
|
| Jelebu non-radioactive rare earths proposal Applicant under state and federal review · Ulu Klawang and Ulu Triang, Negeri Sembilan Malaysia briefing | Waiting for money or permits Environmental review received December 2025; status reported March 2026 | No approved output 357-hectare application | A filed environmental review is evidence of movement, not a mine approval. The project still needs an environmental decision and operating mining scheme. | Cutoff: 2026-08-27Sources and original notes
|
| Pangwa-Chipwi ion-adsorption belt Multiple Chinese-linked and local operators; Kachin Independence Organization and its armed wing control access · Kachin State Myanmar briefing | Operating, but disrupted Kachin Independence Army control since October 2024; status checked August 2026 | No audited mine total Core heavy rare earth feed district | The belt can restart in sections, though tax terms and Chinese technicians decide how much material crosses the border. Reuters' estimate that the region supplies roughly half of the world's mined heavy rare earths describes the wider supply role rather than audited capacity. | Cutoff: 2026-08-27Sources and original notes
|
| Mong Hsat-Mong Yun sites Ownership unverified; United Wa State Army protection and Chinese-speaking operators · Eastern Shan State Myanmar briefing | Producing now Satellite and field evidence to June 2025 | No audited tonnes More than 12 pools at one site and 20 at another | Physical growth is visible, but Reuters could not identify the legal owners. The sites appear to be a substitute for disrupted Kachin feed while remaining tied to Chinese expertise and customers. | Cutoff: 2026-08-27Sources and original notes
|
| India-facing Kachin supply route No committed operator · Kachin to northeast India Myanmar briefing | Study only Contact with state-owned Indian Rare Earths Limited (IREL) reported in December 2024; no commercial route by August 2026 | 0 verified tonnes a year No audited shipment or named separator | Mountain logistics and limited Indian heavy separation capacity keep this below project status. U.S.-linked pitches also lacked a decision and a workable supply chain. | Cutoff: 2026-08-27Sources and original notes
|
| Hasetins Uke expansion Hasetins Commodities · Uke, Nasarawa State Nigeria briefing | Under construction Government inspection 18 June 2026 | Claimed addition of 12,000 tonnes a year Product and feed basis not disclosed | Government and press accounts support a physical construction project. They do not establish that the stated capacity is rare-earth oxide-equivalent output, so it remains outside current supply totals. | Cutoff: 2026-08-27Sources and original notes
|
| Hasetins existing operation Hasetins Commodities · Nasarawa State Nigeria briefing | Output claimed, not verified Claim reported 18 June 2026 | Claimed capacity of 6,000 tonnes a year No public product specification or audited output found | The claimed 6,000-tonne existing operation and 12,000-tonne expansion create the wider 18,000-tonne figure, 12 times the USGS mine estimate. It should remain separate from mine output and market-share totals until feed, product and operating results are published. | Cutoff: 2026-08-27Sources and original notes
|
| National mineral-exploration programme Nigeria Geological Survey Agency · Five-state target programme Nigeria briefing | Study only Current at August 2026 | 15 targets selected Exploration result, not reserve or mine capacity | The programme creates a useful national evidence base, but its public page mixes rare metals with pegmatite exploration. Project-level drilling and tests showing the ore can produce a saleable material are needed before any target enters a supply forecast. | Cutoff: 2026-08-27Sources and original notes
|
| Lovozersky mining complex Rosatom Mining · Murmansk region Russia briefing | Producing now 2025 output reported 20 March 2026 | 5,800 tonnes of loparite concentrate Actual 2025 mineral concentrate, not rare-earth oxide; 12,000-tonne-a-year target for 2030 | Russia's only loparite mine provides the real mining and early-processing base. The double-output plan depends on mine reconstruction and the ore-upgrading plant reaching steady output. | Cutoff: 2026-08-27Sources and original notes
|
| Solikamsk existing chemical chain Solikamsk Magnesium Plant, Rosatom · Perm region Russia briefing | Producing now Process status in 2024 annual report published 2025 | Mixed rare earth concentrate Also recovers titanium, niobium and tantalum products | The plant is a genuine operating processor, but the rare earth stream remains collective rather than a complete slate of individual magnet oxides. | Cutoff: 2026-08-27Sources and original notes
|
| Solikamsk separation expansion Solikamsk Magnesium Plant, Rosatom · Perm region Russia briefing | Study only 2028 completion target reported 18 March 2026 | Individual products: 2,500 tonnes a year Maximum planned output, shifted from the earlier 2027 schedule | The project is intended to split La, Ce, Nd and Pr products from the current mixed stream. State review, construction, trial production and purity data remain. | Cutoff: 2026-08-27Sources and original notes
|
| Glazov NdFeB plant Rosatom Metal Tech and TVEL · Udmurtia Russia briefing | Study only Contract announced 14 February 2024 | Magnet capacity of 1,000 tonnes a year by 2028 Maximum planned output, possible 3,000 tonnes a year after 2030 | A full-cycle magnet line would close a major domestic gap. Its proof is annual sales of customer-approved material and dependable separated feed, not the contract capacity alone. | Cutoff: 2026-08-27Sources and original notes
|
| Tomtor Vostok Engineering, controlled by Rosneft · Yakutia Russia briefing | Stopped or blocked India sample talks reported 16 June 2026 | 11.4-million-tonne ore reserve Probable reserve at 14.5% total rare-earth oxide, not annual production | High grade does not overcome the unbuilt seasonal logistics and remote processor. Full Rosneft control adds a major U.S. sanctions barrier, while sample talks remain far below finance or construction. | Cutoff: 2026-08-27Sources and original notes
|
| Phalaborwa rare earths project Rainbow Rare Earths 85%, with option over the remaining 15% · Phalaborwa, Limpopo South Africa briefing | Testing output Detailed study update 1 July 2026 | 1,850 tonnes a year of NdPr oxide Plus planned Dy/Tb within a grouped heavy-rare-earth product | The project avoids conventional mining and targets separated product. Final separation-circuit design, permits and full funding still gate the 2028 production target. | Cutoff: 2026-08-27Sources and original notes
|
| TechMet financing for Phalaborwa U.S. International Development Finance Corporation (DFC) and TechMet · Portfolio investment supporting South Africa South Africa briefing | Partly funded DFC commitment announced 24 October 2024 | Up to US$50 million equity TechMet investment, not full project funding | DFC's commitment gives Phalaborwa U.S. policy backing. The public summary still expected the project to require a much larger total funding package. | Cutoff: 2026-08-27Sources and original notes
|
| Steenkampskraal Phase 1 Steenkampskraal Holdings and Bora Mining Investments · Western Cape South Africa briefing | Testing output Trial production scheduled August 2026 | 13,400 tonnes a year of concentrate Target above 50% total rare-earth oxide at full design rate | The plant was described as substantially complete, with Industrial Development Corporation (IDC) funding in place. Commercial output was not confirmed by the 27 August cut-off. | Cutoff: 2026-08-27Sources and original notes
|
| Steenkampskraal and Mintek process work Steenkampskraal Monazite Mine and Mintek · South Africa laboratory programme South Africa briefing | Evidence limited Result released 23 June 2026 | High-purity mixed product Laboratory result, not commercial throughput | The programme shows that local ore upgrading chemistry can work on samples. Scale-up and continuous radioactive-waste controls remain unresolved. | Cutoff: 2026-08-27Sources and original notes
|
| Steenkampskraal Phase 2 and 3 Steenkampskraal Monazite Mine · Western Cape South Africa briefing | Study only Sequence current at August 2026 | No funded capacity disclosed Later mixed product and separated oxides | The company plan adds cracking before eventual element separation. Its web dates are stale in places, while strategic finance and National Nuclear Regulator approval remain live gates. | Cutoff: 2026-08-27Sources and original notes
|
| South Africa-EU minerals partnership South African government and European Union · National programme South Africa briefing | Study only Memorandum of understanding signed 20 November 2025 | No rare earth capacity assigned Broader critical-minerals partnership | The partnership favors domestic processing and can support infrastructure. It should not be counted as project finance until a named rare earth facility receives capital. | Cutoff: 2026-08-27Sources and original notes
|
| Southeast Asia raw-material base POSCO International and partners · Malaysia and Laos South Korea briefing | Study only Company plan published 24 March 2026 | About 4,500 tonnes a year of planned supply Separation and refining products across two countries | POSCO presents the base as raw-material supply for a wider chain. The figure remains forecast capacity until projects disclose operating processing lines and recurring product. | Cutoff: 2026-08-27Sources and original notes
|
| POSCO-ReElement US venture POSCO International and ReElement · United States, site to be finalised South Korea briefing | Study only Agreement announced 22 May 2026 | Stage-one separation capacity: 3,000 tonnes a year Separation capacity, expandable to 6,000 tonnes a year | The partners target pilot production in late 2027 and commercial output in 2028. The US$200 million plan is material, although site, feed qualification and construction execution remain open. | Cutoff: 2026-08-27Sources and original notes
|
| LS Eco Energy Vietnam plant LS Eco Energy with proposed Lynas feed · Vietnam South Korea briefing | Study only Reported 25 March 2026 | Samarium metal in the first stage No public comparable annual product capacity | LS targeted operations for the fourth quarter of 2026. Definitive supply and cross-investment agreements still needed negotiation, so the schedule is exposed to slippage. | Cutoff: 2026-08-27Sources and original notes
|
| JS Link Kuantan magnet plant JS Link with Lynas investment and feed · Kuantan, Malaysia South Korea briefing | Funded, work not started Agreement reported 6 July 2026 | 3,000 tonnes a year of neodymium-iron-boron (NdFeB) magnets Maximum planned sintered-magnet output | Lynas will invest about A$50 million and supply material through January 2038. The project has a clearer feed and capital route than many magnet announcements, with trial production still to be demonstrated. | Cutoff: 2026-08-27Sources and original notes
|
| Per Geijer LKAB · Kiruna, Norrbotten Sweden briefing | Study only Resource update 30 March 2026 | 2.2 million tonnes of rare-earth oxide in the ground Contained in an inferred mineral resource, not annual output or reserve | Existing Kiruna infrastructure is a major advantage. A concession, environmental permit, rights-compatible design, reserve study, full construction funding and formal approval to build remain before construction. | Cutoff: 2026-08-27Sources and original notes
|
| Luleå demonstration plant LKAB · Luleå Industrial Park Sweden briefing | Under construction Permit granted 26 May 2026 | Demonstration scale Targeted operation by the end of 2026 | The demo can validate recovery of phosphorus and rare earths from apatite. Continuous run data and product quality, not mechanical completion alone, will decide whether it supports a commercial build. | Cutoff: 2026-08-27Sources and original notes
|
| Malmberget apatite plant LKAB · Gällivare, Norrbotten Sweden briefing | Waiting for money or permits Ruling 15 June 2026; appeal disclosed 13 August 2026 | Apatite feed for Luleå Full-scale feed route, not current rare earth output | The environmental ruling includes the feed plant but was under appeal at the cut-off. A final permit, full construction funding, formal approval to build and construction remain distinct gates. | Cutoff: 2026-08-27Sources and original notes
|
| ReeMAP commercial scale-up LKAB · Malmberget and Luleå Sweden briefing | Study only 2030s timing in annual report published 23 April 2026 | Mixed rare earth oxide concentrate No final commercial capacity disclosed in the current plan | The demonstration plant is intended to provide the technical basis. Feed permits, a commercial study, individual separation route and finance must line up before full-scale. | Cutoff: 2026-08-27Sources and original notes
|
| Norra Kärr Leading Edge Materials and Greenna Mineral · Jönköping County Sweden briefing | Study only Government decision 27 June 2026 | 5,340 tonnes a year of mixed rare-earth oxide 2021 early study case, not current guidance or production | The concession moves the project forward, but a full environmental permit, Natura 2000 protected-habitat review, updated study, offsite processing plan, full construction funding and formal approval to build remain. | Cutoff: 2026-08-27Sources and original notes
|
| Ngualla mine and concentrator Shenghe-controlled Mamba Minerals; Tanzania 16% free-carried · Songwe Region Tanzania briefing | Waiting for money or permits Ownership completed 30 September 2025 | 16,200 tonnes a year of total rare-earth oxide Contained in planned concentrate under the 2022 study | The ore reserve and licence are established. No formal post-takeover approval to build, full construction funding or main construction notice was found by 27 August 2026, so the output remains a design case. | Cutoff: 2026-08-27Sources and original notes
|
| Ngualla enabling works Mamba Minerals · Ngualla site and access corridor Tanzania briefing | Study only Resettlement plan status reported 14 March 2025 | No commercial tonnes Hydrology, airstrip and access work | Peak disclosed compensation scheduling and early site tasks before the takeover. Completion under Shenghe needs fresh evidence because preparatory work does not equal main construction. | Cutoff: 2026-08-27Sources and original notes
|
| Mamba Refinery option Shenghe-controlled former Peak group · Tanzania, site not finally sanctioned Tanzania briefing | Study only No public sanction by 27 August 2026 | No defined capacity Potential domestic intermediate or oxide route | A refinery entity exists in the ownership structure, while the binding commercial route still awards Shenghe all concentrate. Treat domestic separation as an option until a site, budget and construction decision are published. | Cutoff: 2026-08-27Sources and original notes
|
| Wigu Hill Tanzanian state control after Montero expropriation dispute · Morogoro Region Tanzania briefing | Stopped or blocked International arbitration case discontinued 31 March 2025 | No current production case US$27 million settlement completed | Tanzania paid the final settlement instalment in March 2025 and the arbitration was discontinued. The episode is a live reminder that licence stability affects the cost of capital long after a dispute ends. | Cutoff: 2026-08-27Sources and original notes
|
| Fungoni and Tajiri mineral sands Shenghe through Nyati Mineral Sands · Tanzanian coast Tanzania briefing | Evidence limited Portfolio status disclosed 30 May 2025 | No rare earth tonnes disclosed Heavy-mineral-sands assets, not Ngualla output | Shenghe said Fungoni had started operations and Tajiri resettlement valuation was nearly complete. The assets add local logistics and government experience, but they should not be counted as rare earth supply. | Cutoff: 2026-08-27Sources and original notes
|
| Magnequench Korat Neo Performance Materials · Nakhon Ratchasima Thailand briefing | Producing now Capacity disclosed 10 March 2022; operating footprint checked August 2026 | 1,800 tonnes a year NdFeB powder and compound capacity | Korat is the strongest documented Thai rare earth manufacturing asset. Its powder feeds components made in later factory steps, but the capacity is neither mine output nor a finished sintered-magnet total. | Cutoff: 2026-08-27Sources and original notes
|
| Xinyuan Rare Earth Thailand Chinese-linked ownership in the last USGS asset record · Ban Khai, Rayong Thailand briefing | Current status unverified USGS 2020-2021 industry record; fresh verification needed in 2026 | 3,000 tonnes a year of oxides Older planned or reported capacity; 2,000 tonnes a year of metals and alloys also cited | The old yearbook gives a useful asset lead, not proof of current output ready to sell. A current licence and owner should precede any operating label. A production filing would settle the output question. | Cutoff: 2026-08-27Sources and original notes
|
| Kabin Buri chemical processing plant Enuo; Hastings pursuing a 49% interest · Prachinburi Thailand briefing | Waiting for approvals Quarterly update authorized 24 July 2026 | 12,000 tonnes a year of mixed rare-earth chloride Gross mixed chloride design from 10,000 tonnes a year of African monazite feed | The expanded design and feed agreement create a defined route. Transaction close and licence changes still sit ahead of trial production, with the first quarter of 2027 as the company target. | Cutoff: 2026-08-27Sources and original notes
|
| Southern tin-tailings prospects Thailand Department of Mineral Resources (DMR) inventory and various legacy mine areas · Southern Thailand Thailand briefing | Study only DMR sources accessed 27 August 2026 | No reserve or annual-output case Monazite and xenotime in placer or tailings systems | Occurrences are well documented, while no current published national mine record ties them to the USGS 4,800-tonne estimate. | Cutoff: 2026-08-27Sources and original notes
|
| Jarin tin deposit rare earth by-product Jarin tin operation and research partners · Kanchanaburi Thailand briefing | Study only Study published 3 May 2024 | No commercial rare earth output Accessory monazite and xenotime | The minerals occur in the tin system, though recovery and product economics remain unproven. It belongs in exploration rather than supply. | Cutoff: 2026-08-27Sources and original notes
|
| Mountain Pass mine and separation complex MP Materials · Mountain Pass, California United States briefing | Producing now Status filed 26 February 2026 | Concentrate and separated NdPr oxide The only US rare earth mine operating at this scale | The complex produced 50,692 tonnes of rare-earth oxide in concentrate during 2025. Separated NdPr output reached 2,599 tonnes, so the processing line reaching steady output remains the key operating test. | Cutoff: 2026-08-27Sources and original notes
|
| Independence and 10X magnet program MP Materials · Fort Worth and Northlake, Texas United States briefing | One plant operating; one planned Status filed 26 February 2026 | Integrated NdFeB magnets Metal, alloy and magnet steps brought together | Independence started industrial magnet manufacturing in December 2025 and is being expanded toward 3,000 tonnes a year. The planned 10X facility adds 7,000 tonnes, with trial production expected in 2028. | Cutoff: 2026-08-27Sources and original notes
|
| White Mesa rare earth circuit Energy Fuels · Blanding, Utah United States briefing | Producing now; expansion building Construction update 29 July 2026 | NdPr now; Dy and Tb planned Monazite processing inside an existing licensed mill | The current circuit is designed for up to 1,000 tonnes of NdPr oxide a year. Construction of commercial heavy separation began in July 2026, while the larger phase-two expansion remains a project rather than operating capacity. | Cutoff: 2026-08-27Sources and original notes
|
| San Marcos magnet plant Noveon Magnetics · San Marcos, Texas United States briefing | Producing now Financing update 19 January 2026 | Sintered NdFeB magnets Uses both mined and recycled magnetic material | Noveon closed a US$215 million financing round to expand US production. Its binding Nidec agreement runs for five years. Potential volume exceeds 1,000 tonnes, evidence of customer demand rather than a factory rating alone. | Cutoff: 2026-08-27Sources and original notes
|
| Stillwater and Blacksburg magnet buildout USA Rare Earth · Oklahoma and South Carolina United States briefing | Testing output; expansion planned Latest site announcement 2 June 2026 | Sintered NdFeB magnets and alloy A staged domestic manufacturing network | Stillwater is targeting 600 tonnes a year by the fourth quarter of 2026. Blacksburg is designed for 6,400 tonnes of magnets a year, with trial production targeted for 2028. | Cutoff: 2026-08-27Sources and original notes
|
| Round Top heavy rare earth project USA Rare Earth · Hudspeth County, Texas United States briefing | Study only Quarterly update 10 August 2026 | Potential heavy rare earth feed No commercial mine output yet | The company expects its definitive feasibility study in late 2026 and targets commercial production in late 2028. Both dates are corporate targets, and neither should be counted as current mine supply. | Cutoff: 2026-08-27Sources and original notes
|
| VAC Sumter magnet facility Vacuumschmelze, proposed acquisition by Energy Fuels · Sumter, South Carolina United States briefing | Producing now Acquisition agreement announced 23 June 2026 | NdFeB and SmCo permanent magnets An experienced producer inside a proposed integrated group | The facility has 2,000 tonnes of annual permanent-magnet capacity. Energy Fuels describes it as scalable to 12,000 tonnes. The VAC acquisition was not complete at the data cut-off, so the expansion remains contingent. | Cutoff: 2026-08-27Sources and original notes
|
| Dong Pao Vietnamese state mineral framework; development partner unresolved · Lai Chau Vietnam briefing | Study only Master-plan asset; no sustained commercial output by August 2026 | No audited tonnes a year Academic resource is not current production | Dong Pao has substantial light rare earth-rich geology but no demonstrated operating mine. A transparent award and study detailed enough for lenders remain ahead. Financing would follow them. | Cutoff: 2026-08-27Sources and original notes
|
| Bac Nam Xe and Nam Nam Xe Vietnamese state mineral framework · Lai Chau Vietnam briefing | Study only Included in 2023 master plan; status checked August 2026 | No verified commercial output Monazite and bastnaesite systems | Mineralogy supports more technical work, while no current filing demonstrates a financed commercial plant. Planning-list inclusion should stay out of operating capacity. | Cutoff: 2026-08-27Sources and original notes
|
| Yen Phu and Vietnam Rare Earth processing Thai Duong Group and Vietnam Rare Earth JSC · Yen Bai Vietnam briefing | Stopped or blocked Arrests October 2023; wider case July 2024 | No current audited output Flagship local processing route suspended | The case involved alleged unlicensed ore trade and forged tax records. Reuters later reported Vietnam Rare Earth suspended, so prior partnerships do not establish a current operating chain. | Cutoff: 2026-08-27Sources and original notes
|
| Shin-Etsu Magnetic Materials Vietnam Shin-Etsu Chemical · Hai Phong Vietnam briefing | Producing now Operating since 2016; annual report update July 2025 | 2,200 tonnes a year of magnets Announced capacity after expansion, not current utilization | The plant integrates refining or recycling with pressing and sintering. Its industrial value is established, though feed origin should not be assumed to be Vietnamese ore. | Cutoff: 2026-08-27Sources and original notes
|
| LS Eco Energy rare earth metal plant LS Eco Energy with preliminary Lynas cooperation · Ho Chi Minh City area Vietnam briefing | Study only Agreement reported 25 March 2026; company target: fourth quarter of 2026 | Capacity not disclosed Initial samarium metal from imported Lynas oxide | The route could supply non-Chinese samarium-cobalt magnet supply chains sooner than a Vietnamese mine opens. A preliminary agreement and year-end target remain below commercial production until batches ready to sell ship. | Cutoff: 2026-08-27Sources and original notes
|
Method, citation and change record
The first edition extracts structured project cards and Australia's project table from the existing country briefings. It retains the original reporting cutoffs and source notes, including source dates where they were supplied. The downloadable records include the source-file checksum for reproducibility. Compilation does not represent a new review of the primary documents.
Cite as: EarthRarest, Rare earth projects tracker, compilation 19 October 2026, with the relevant row's original data cutoff and primary source. Do not remove a product or financing qualification when quoting a row.
19 October 2026: first consolidated edition; no source claim refreshed. The table has no automatic update schedule. A later refresh should identify changed rows and their new evidence. For national mine output, see production by country.