Rare Earth Race · Country Briefing

Sweden's big rare-earth find is unlikely to be mined this decade.

The nearer route is recovery from material the iron-ore industry already handles. Per Geijer's 2.2 million tonnes remain a resource in the ground, not a mine.

Updated 30 August 202620 minute readProject data cutoff 27 August 2026Price reference 28 August 2026
On this pageTakeaway

Sweden's first saleable rare earth product may come from material its iron ore industry already moves. LKAB is building a demonstration plant in Luleå to recover phosphorus and a mixed rare earth product from apatite left by existing operations. The plant had its environmental permit and was targeting start-up by the end of 2026. 8 9

Per Geijer is the larger geological story, with 2.2 million tonnes of rare earth oxide contained in an inferred resource. That is material still in the ground, not a reserve or annual production. A commercial mine is unlikely before 2030. Norra Kärr offers possible dysprosium and terbium feed and an older study case of 5,340 tonnes a year of mixed oxide, but still needs environmental approval, updated engineering and construction finance. 2 18 Sweden can prove a useful recovery process this decade. Individual oxides, metals and qualified magnets remain later steps.

The country in four dates

Waste recovery is closer than a new underground mine.

Reported output, current events, company targets and our forecasts are kept in separate boxes. NdPr means neodymium and praseodymium reported together. Dy/Tb means dysprosium and terbium reported together.

Latest official position · 2025

No country mine-output line is reported.

  • No reported outputcommercial rare-earth mining1
  • 2.2 million tonnesinferred rare-earth resource at Per Geijer; not a reserve2Scale: This is an inferred resource in the ground, not a reserve or annual output. A production share would be invalid.

What changed in 2026

Permits moved, while appeals still mattered.

  • Permit receivedLuleå demonstration plant9
  • AppealedMalmberget ruling12
  • Government decisionNorra Kärr concession process17

Next credible opening

A test plant should move before a mine.

  • Company targetEnd-2026Luleå demonstration start-up target8
  • Company targetEnd-2027continuous campaign target10

2030 view

Per Geijer remains a 2030s project.

  • EarthRarest viewNo commercial Per Geijer mineour main forecast3
  • ReeMAP demonstrationmore plausible source of first material this decade8

Strategic metals already in the picture

Rare earths are not the whole story.

Data and sources
Te
48 tonnesTellurium in concentrate, 2025; not a refinery share

Projects first

Waste recovery could produce before a new underground mine

Per Geijer

LKAB · Kiruna, Norrbotten

Study only

Resource update 30 March 2026

2.2 million tonnes of rare-earth oxide in the ground

Contained in an inferred mineral resource, not annual output or reserve

Existing Kiruna infrastructure is a major advantage. A concession, environmental permit, rights-compatible design, reserve study, full construction funding and formal approval to build remain before construction. 2 3 6

Luleå demonstration plant

LKAB · Luleå Industrial Park

Under construction

Permit granted 26 May 2026

Demonstration scale

Targeted operation by the end of 2026

The demo can validate recovery of phosphorus and rare earths from apatite. Continuous run data and product quality, not mechanical completion alone, will decide whether it supports a commercial build. 8 9

Malmberget apatite plant

LKAB · Gällivare, Norrbotten

Waiting for money or permits

Ruling 15 June 2026; appeal disclosed 13 August 2026

Apatite feed for Luleå

Full-scale feed route, not current rare earth output

The environmental ruling includes the feed plant but was under appeal at the cut-off. A final permit, full construction funding, formal approval to build and construction remain distinct gates. 12 13

ReeMAP commercial scale-up

LKAB · Malmberget and Luleå

Study only

2030s timing in annual report published 23 April 2026

Mixed rare earth oxide concentrate

No final commercial capacity disclosed in the current plan

The demonstration plant is intended to provide the technical basis. Feed permits, a commercial study, individual separation route and finance must line up before full-scale. 11 14

Norra Kärr

Leading Edge Materials and Greenna Mineral · Jönköping County

Study only

Government decision 27 June 2026

5,340 tonnes a year of mixed rare-earth oxide

2021 early study case, not current guidance or production

The concession moves the project forward, but a full environmental permit, Natura 2000 protected-habitat review, updated study, offsite processing plan, full construction funding and formal approval to build remain. 17 18 19

Material by material

What Sweden supplies now, what could change by 2030, and China's share

Each card begins with the finding. The numbers and their limits sit underneath it.

Every bar runs from 0% to 100%. A solid bar is directly comparable. A shaded bar is an estimate or uses a different type of output. Where no reliable percentage exists, the card says so instead of drawing a false zero.

Sweden nowIf projects openChina todayShaded: estimate or different output
Mixed

Industrial by-product recovery may lead mining

Mixed rare earth oxidesFeed for later rare-earth separation

No published shareNo comparable percentage exists for current supply, planned supply or the China comparison at the same product stage.
NowNo commercial mixed-oxide output
If projects open2021 Norra Kärr study case: 5,340 tonnes a year of mixed oxide; not funded production guidance

What it means: Existing industrial infrastructure can reduce risk, but neither route is current saleable oxide. 8, 18, 23

What these figures mean

Sweden has no commercial mine output, while LKAB is installing a demonstration route using apatite from iron-ore operations. Norra Kärr's older early study models 5,340 tonnes a year of mixed rare-earth oxide after a new concession.

China figure: No like-for-like individual-material China share is published for this product stage.

Nd+Pr

Contained potential without a current product split

NdPr: Neodymium and PraseodymiumPermanent magnets for vehicles, wind and industry

NdNeodymiumPrPraseodymium
Sweden nowNo reliable global percentage
If projects openNo reliable global percentage
China today91% for Nd, Pr, Dy and Tb together (2024)
NowAmount not published
If projects openAmount not published

What it means: Sweden's near-term evidence is a process run, not a national NdPr forecast. 2, 9, 22

What these figures mean

Per Geijer's 2.2 million-tonne figure is rare-earth oxide in the ground in an inferred resource, not annual NdPr supply. The Luleå demonstration must prove continuous product quality before commercial design.

China figure: China refined 91% of neodymium, praseodymium, dysprosium and terbium together in 2024. This is not an individual-material share.

Dy+Tb

Norra Kärr carries the clearer heavy-rare earth case

Dy + Tb: Dysprosium and TerbiumHigh-temperature permanent magnets

DyDysprosiumTbTerbium
Sweden nowNo reliable global percentage
If projects openNo reliable global percentage
China today91% for Nd, Pr, Dy and Tb together (2024)
NowNone reported
If projects openAmount not published

What it means: A concession raises project credibility but does not create heavy-oxide supply. 17, 18, 19, 22

What these figures mean

No current Swedish separated Dy or Tb output is reported. Norra Kärr still needs environmental permission, an updated study, offsite processing, finance and final build decision.

China figure: China refined 91% of neodymium, praseodymium, dysprosium and terbium together in 2024. This is not an individual-material share.

P + rare earth

The coproduct route is Sweden's industrial advantage

Phosphate and rare earthsFertiliser feed and rare-earth recovery

No published shareNo comparable percentage exists for current supply, planned supply or the China comparison at the same product stage.
NowAmount not published
If projects openAmount not published

What it means: A by-product chain can beat a remote stand-alone mine if permits, continuous recovery and separation all work. 14, 13, 23

What these figures mean

ReeMAP aims to recover phosphorus and rare earths from apatite already linked to LKAB mining. Malmberget feed permitting was under appeal at the cut-off.

China figure: No like-for-like individual-material China share is published for this product stage.

China oxide price guide

Indicative domestic midpoints, 28 August 2026, per kilogram

LanthanumUS$0.72
CeriumUS$1.87
SamariumUS$2.17
YttriumUS$7.75
GadoliniumUS$25.62
NdPrUS$95.56
DysprosiumUS$191.78
TerbiumUS$889.95
Per kg of oxide. Purity, tax, delivery point, export licensing and contract terms can change a quote by multiples. These are not local sale-price forecasts. Source: SMM.

Strategic metals beyond rare earths

Sweden's other strategic metals

Each card states the type of output and year. The bars compare this country with the market leader at the same step whenever the data allows it. A data gap is not zero.

Te
2025 concentrate estimate

Sweden reports tellurium in concentrate, a different stage from the refinery totals in the global comparison.

Tellurium: Thin-film solar panels, thermoelectric devices and specialist alloys.

48 tonnesNo refinery share
ChinaMarket leader or closest benchmark
80%

This country's percentage is not public. The bar shows the market leader for context.

Compare all eight strategic metals

The conversion test

Where Sweden actually sits in the chain

A deposit is only the first step. Statuses below describe operating capability at the data cut-off, not announced ambition.

01
Existing residuals first

Mine and feed

Malmberget residuals can supply test apatite before Per Geijer is mined. The Malmberget permit covering the feed plant was appealed. 12 13

02
Demo trial production next

Mixed oxide

Luleå construction began in January 2025 and process equipment was being installed in 2026. The target was operation by year-end. 8 9

03
External dependency

Individual separation

LKAB plans a mixed rare earth oxide concentrate. Its REEtec investment offers a Nordic link but does not establish Swedish commercial individual oxide output. 14 15

04
Not established at scale

Metals and alloys

The oxide-to-metal and alloy layer remains outside LKAB's disclosed Swedish process scope.

05
European gap

Permanent magnets

GKN cancelled a planned European magnet factory in February 2026, showing that progress in mining and early processing still lacks a robust customer for approved magnets. 16

The numbers

The mine-output number in context

USGS 2025 estimates cover total rare earth oxide equivalent. The chart does not measure refining or magnet output.

Leading mine producers

World share and tonnes, 2025 estimate
China 270,000 tonnes · 69.2% of world
United States 51,000 tonnes · 13.1% of world
Australia 29,000 tonnes · 7.4% of world
Myanmar 22,000 tonnes · 5.6% of world
Sweden Not reported
Every rail runs from 0% to 100% of world mine output. The label also gives tonnes. World total: about 390,000 tonnes in 2025; trade-derived estimates can be revised.

LKAB's 2026 update put the Per Geijer mineral resource at about 1.3 billion tonnes. Contained rare earth oxide remained at 2.2 million tonnes, still an inferred figure rather than a reserve. The industrial proposition also includes iron and phosphorus, which can spread costs across several products. 2 Kiruna already supplies rail and power, while its workforce brings underground mining knowledge that many European deposits lack.

The rare earth component remains inferred because modifying factors have not converted it to an ore reserve. Those factors test mining method and recovery before a reserve can be declared. Price assumptions and environmental effects also matter, as do permits and social constraints. A large contained-oxide number can coexist with zero output ready to sell for many years.

LKAB submitted an exploitation concession application for Luossavaara K nr 2 in 2023. The public tracker described continuing design studies and consultation, with environmental application work under way. A county response was expected in August 2026, another administrative step rather than approval. Mining Inspectorate action was indicated for late November, although no final concession decision was identified at this cut-off. 3

The EU combined Per Geijer with Malmberget under one Strategic Project in March 2025, with Luleå as the processing component. 4 Strategic Project status can coordinate a difficult sequence and set indicative time limits. It cannot create a reserve or issue Sweden's environmental permit, while an affected rights-holder still retains the right to appeal.

An April 2026 Stockholm Environment Institute case study found a significant risk that Per Geijer could violate Gabna's Indigenous rights. Mine infrastructure could affect the corridor linking winter and summer grazing grounds and further fragment the remaining connected land. The report assessed major or severe effects across the six conditions it examined. 6

Compensation for one disturbed parcel cannot solve the problem. Reindeer husbandry depends on movement and seasonal access, while snow or ice can close one route and force herders to adjust elsewhere. A corridor that looks narrow on a mine map can hold a landscape-scale function that is difficult to replace elsewhere.

SEI identified gaps in consultation and community influence, alongside an incomplete human rights assessment. Reuters reported that Gabna was prepared to challenge approvals in court. LKAB acknowledged the impact and said it sought dialogue with Gabna, with compensation and practical solutions on the table. 7 The concession and environmental stages can both be appealed, so a rushed decision may lengthen rather than shorten the schedule.

Sweden's July 2026 strategy framed critical mining as a national security interest. That increases political urgency but does not lower the legal or moral standard. A durable Per Geijer plan needs a rights-compatible design and an agreement with the affected community, not a claim that security automatically outweighs land use. 20

Strategic status can speed administration. It cannot make a migration corridor optional.

What the numbers say

LKAB started construction of the Luleå demonstration plant in January 2025. Process equipment installation inside the plant was under way by April 2026. The Land and Environment Court granted its environmental permit on 26 May, and the county tracker later recorded the ruling as final. LKAB targeted operation in autumn or by the end of 2026. 8 9

The plant is designed to test extraction of phosphorus and all 17 rare earth elements from apatite concentrate. This is a meaningful industrial step because it can produce real recovery and reagent data. Impurity behaviour and product quality can then be measured against actual feed. A trial production run is not yet a commercial refinery, and the reported SEK 800 million demonstration investment should not be shown as full-scale plant construction cost. 10

Initial feed can come from existing Malmberget iron ore residuals. The new Malmberget environmental ruling includes the intended apatite plant, but LKAB reported in August that the decision had been appealed. 12 13 Existing material can still enter the demo while that case proceeds, but a durable full-scale chain needs a final feed permit and separate investment decision.

The annual report published in 2025 places industrial scale-up in the following decade. 11 That newer schedule is more credible than older language pointing to commercial production around 2029. The demonstration is therefore the near-term test, while full-scale remains a separate project with its own finance and construction gates.

The most important Swedish rare earth result of 2027 may be a product assay, not a mine opening.

EarthRarest forecast

LKAB describes the intended ReeMAP product as a mixed rare earth oxide concentrate. 14 The material is more advanced than mineral concentrate and could feed a separation plant, though individual high-purity magnet oxides still require later processing.

A complete chain starts with individual separation and oxide-to-metal conversion. Neodymium-iron-boron alloy is cast into thin strips before it is pressed and heat-treated into magnets. Machining and coating prepare the magnets for customer approval before shipment. Each step has a different yield and capital need; technical ownership varies as well. Reporting only the contained rare earth tonnes at Per Geijer hides the stages where China's market power is strongest.

LKAB's investment in Norway's REEtec is an attempt to create a Nordic separation route. 15 Cross-border integration is not a weakness if the plant operates and contracts hold. It does mean a Swedish mine or Luleå plant should not be labelled a domestic mine-to-magnet chain.

GKN cancelled its planned European magnet factory in February 2026, exposing the fragility of later processing and factory plans. 16 Sweden's credible win by 2030 is a stable mixed-oxide source connected to commissioned European separation and magnet partners, without assuming complete self-sufficiency inside one national border.

The Swedish government granted Norra Kärr an exploitation concession on 27 June 2026. Its term runs for 25 years, letting the deposit proceed into deeper evaluation and environmental review. It is neither an operating permit nor a final investment decision, and mine construction still needs separate permission. 17

Conditions protect Hålaveden and the Lake Vättern drinking water interest. The Holkaberg Natura 2000 area and total defence receive protection as well. Under the redesigned concept, chemical processing moves away from the mine and the proposed footprint shrinks. The county says substantial investigation remains and that the environmental process must define the actual scale and protections. 19

A company early study from 2021 modelled about 5,340 tonnes a year of mixed rare-earth oxide from part of an inferred resource. 18 Its 26-year mine life remains preliminary because the model relies on older assumptions. An updated study must define the offsite chemical location and water design. Waste controls and recoveries also need work, followed by finance and a purchase agreement.

Norra Kärr matters because its basket includes heavy rare earths such as dysprosium. The strategic value can support policy and customer interest, but it cannot replace a full Environmental Code review beside Lake Vättern or turn an early study into a reserve.

Government help

How the government is helping projects get built in Sweden

Loans, grants, guaranteed buyers and minimum prices can help a project get built. A promise counts only when the money or contract is committed.

EU Strategic ProjectRecognisedPer Geijer and related value chain
Norra Kärr concession25 yearsStill needs environmental permit
Mine outputNoneNo current commercial rare earth mine
Public price floorNoneNo Swedish oxide minimum disclosed
MeasureWhat it doesWho receives itWill it move the project?
EU Critical Raw Materials ActStrategic Project recognition and permitting supportPer Geijer is positioned inside Europe's diversification policy.Named projects meeting strategic criteria.Recognition can reduce friction, not remove lawEnvironmental, Indigenous-rights and finance gates remain. 4, 3
Mining as a national-security interestHigher policy priority for domestic critical mineralsSweden has explicitly linked mining capacity to supply security.Mines and industrial recovery projects with a credible local chain.Priority does not equal approvalThe useful test is a final permit and funded construction schedule. 20
Norra Kärr mining concessionTwenty-five-year project rightThe 2026 decision allows further development but not immediate production.The named Norra Kärr project.One gate closed, several remainNatura 2000 protected-habitat review, environmental permission, updated engineering and final build decision still separate it from supply. 17, 18
Sámi rights and environmental reviewRights-compatible project designPer Geijer affects a Gabna Sámi migration corridor and faces material rights risk.LKAB and any project crossing reindeer-herding land.Social permission is schedule-criticalFaster permitting cannot lawfully erase consultation or mitigation obligations. 6, 7

EarthRarest forecast

What to watch through 2030

These are dated editorial predictions, not company guidance or investment advice. Each includes the evidence that would force a rethink.

By 31 December 2027

The Luleå demo documents a continuous rare earth and phosphorus process campaign

Construction and equipment installation were advanced, and the environmental permit was in place. Full commercial scale remains a later 2030s decision. 8 9 11

ConfidenceHigh
What would change this view

Revise if trial production slips beyond 2027 or if disclosed runs fail to produce a consistent mixed oxide product.

At 31 December 2030

Per Geijer has not recorded sustained commercial rare earth production

The rare earth resource remains inferred, with concession, environmental, rights, feasibility, financing and construction gates ahead. LKAB has described a roughly decade-long path. 2 5 6

ConfidenceHigh
What would change this view

Revise if a final concession survives appeal, LKAB and Gabna publish a rights-compatible agreement, a reserve and feasibility study are declared, followed by full construction funding and formal approval to build.

By 31 December 2029

Norra Kärr has not received a fully financed construction notice to proceed

The concession is recent and the economic case is still a 2021 early study. Environmental review remains open, including the Natura assessment. Offsite processing also needs finance and a purchase agreement. 17 18 19

ConfidenceMedium
What would change this view

Revise if an updated feasibility study, final permits, committed debt and equity and a binding engineering and construction notice to proceed are disclosed.

Method and evidence

What the numbers mean

Inferred is not reserve
Per Geijer's contained oxide sits inside an inferred resource. EarthRarest does not use it as Sweden's national reserve or annual output. 2 1
Demo and commercial scale
Luleå trial production can validate a process design without establishing full-scale commercial output. Full-scale ReeMAP is tracked as a separate 2030s investment case. 11
Strategic status and rights
EU Strategic Project and Swedish national security labels do not replace a concession, environmental permit, Indigenous-rights review or appeals. 4 6
Sources used for this briefing
  1. Mineral Commodity Summaries 2026: Rare Earths, U.S. Geological Survey, 6 February 2026, version 1.3 May 2026. Sweden is not separately listed for production or reserves.
  2. LKAB reports improved Mineral Resources, LKAB, 30 March 2026. Per Geijer resource and contained inferred rare earth oxide.
  3. Support in permit processes for net zero and critical raw material projects, County Administrative Board of Norrbotten, Accessed 27 August 2026. Per Geijer concession stage, public timetable and Luleå permit tracking.
  4. Commission Decision EU 2025/840 recognising Strategic Projects under the Critical Raw Materials Act, European Commission, 25 March 2025. Integrated strategic designation for Malmberget, Per Geijer and Luleå.
  5. Sweden's LKAB says it could meet 18% of Europe's rare earth needs with Per Geijer mine, Reuters, 28 January 2025. Company demand-share claim, decade-long development and remaining approvals.
  6. How risks to Indigenous rights in the reindeer husbandry area can be managed in mining projects: Per Geijer case study, Stockholm Environment Institute, 15 April 2026. Impacts on the Gabna Sámi reindeer-herding community, rights risks and consultation findings. DOI 10.51414/sei2026.011.
  7. LKAB plan for Swedish rare earths mine could breach Sámi rights, report says, Reuters, 15 April 2026. Rights-holder response, LKAB response and appeal risk.
  8. Progress in Luleå for the investment in critical minerals, LKAB, 21 April 2026. Construction start, equipment installation and demo process scope.
  9. LKAB receives the go-ahead for its critical minerals initiative, LKAB, 26 May 2026. Environmental permit and target for demo operation.
  10. LKAB constructs facility for critical minerals, the first of its kind in Europe, LKAB, 24 October 2024. SEK 800 million demo investment and 2030s scale-up framing.
  11. LKAB Annual and Sustainability Report 2025, LKAB, 23 April 2026. Demo schedule and commercial scale-up during the 2030s.
  12. LKAB granted environmental permit for operations in Gällivare, LKAB, 15 June 2026. Malmberget ruling and apatite feed plant scope.
  13. Interim report April-June 2026, LKAB, 13 August 2026. Malmberget environmental ruling was appealed.
  14. Rare earth elements, LKAB, Accessed 27 August 2026. Planned product is a mixed rare earth oxide concentrate.
  15. LKAB becomes largest owner in REEtec, LKAB, 19 January 2022. Nordic separation investment and partnership context.
  16. GKN cancels plans for magnet factory in setback to Europe's rare earth aims, Reuters, 27 February 2026. Current evidence of Europe's permanent magnet capacity gap.
  17. The government decides that the deposit at Norra Kärr may be investigated further, Government of Sweden, 27 June 2026, corrected 9 July 2026. 25-year concession, remaining environmental review and protective conditions.
  18. Leading Edge Materials granted 25-year mining lease for Norra Kärr heavy rare earth elements project, Leading Edge Materials, 29 June 2026. 2021 early study scope and next study, permit, purchase agreement and finance gates.
  19. Norra Kärr, County Administrative Board of Jönköping, Accessed 27 August 2026. Remaining investigation, Vättern, Natura and environmental permit context.
  20. Sweden declares mining a national security interest to counter dependence on China, Reuters, 23 July 2026. National security strategy, faster process tools and Sámi land-use tension.
  21. SMM Rare Earth Oxides, assessed 28 August 2026. Domestic-China oxide midpoint indications used in the material price board.
  22. International Energy Agency, Rare Earth Elements. China shares in 2024: 91% of combined Nd, Pr, Dy and Tb refining and 94% of sintered permanent magnets. These are group shares, not an individual share for each element.
  23. European Commission, Study on the Critical Raw Materials for the EU 2023. Processing-share estimates use the 2016 to 2020 reference period and are labelled as reference values, not current 2026 shares.
Editorial artwork is illustrative and does not depict a named project site. Production and reserve figures are dated estimates. EarthRarest provides research and commentary, not personalised investment advice.

Continue when you’re ready

Bring us your questions.

Talk through the metals, the buying process, storage or resale with EarthRarest.

Speak with us How buying works